2026-06-12 - 2026-ELEC-0002278
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-06-10 - 2026-COMMCON-0000227
08:00 AM - 10:00 AM: Document Review Inspection
08:00 AM - 10:00 AM: 109 - Other
2026-06-10 - 2026-MECH-0001063
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-06-09 - 2026-ELEC-0002278
12:00 PM - 02:00 PM: 308 - Ceiling
2026-06-09 - 2026-PLUMB-0001346
01:00 PM - 03:00 PM: 402 - Final - Plumbing
2026-06-05 - 2026-COMMCON-0000227
01:00 PM - 03:00 PM: 112 - Frame
2026-06-04 - 2026-ELEC-0002278
10:00 AM - 12:00 PM: 302 - Partial Rough
2026-05-27 - 2026-MECH-0001063
12:00 PM - 02:00 PM: 903 - Rough
2026-05-19 - 2026-ELEC-0002278
01:00 PM - 03:00 PM: 302 - Partial Rough
2026-05-18 - 2026-PLUMB-0001346
11:00 AM - 01:00 PM: 401 - Rough
2026-04-02 - 2026-PLUMB-0001346
01:00 PM - 03:00 PM: 400 - Groundwork