2026-06-12 - 2026-COMMCON-0000183
12:30 PM - 02:30 PM: 107 - Drywall
2026-06-11 - 2026-COMMCON-0000183
09:00 AM - 11:00 AM: 106 - Batt Insulation
2026-06-11 - 2026-ELEC-0000941
08:30 AM - 09:30 AM: 303 - Full Rough
TBD: 308 - Ceiling
2026-06-08 - 2026-COMMCON-0000183
09:00 AM - 11:00 AM: 107 - Drywall
2026-06-05 - 2026-COMMCON-0000183
10:30 AM - 12:30 PM: 107 - Drywall
10:30 AM - 12:30 PM: 112 - Frame
2026-06-05 - 2026-ELEC-0000941
11:00 AM - 01:00 PM: 302 - Partial Rough
TBD: 303 - Full Rough
2026-06-04 - 2026-COMMCON-0000183
09:00 AM - 11:00 AM: 112 - Frame
2026-06-02 - 2026-COMMCON-0000183
10:30 AM - 12:30 PM: 100 - Footing
2026-06-01 - 2026-COMMCON-0000183
10:30 AM - 12:30 PM: 112 - Frame
2026-05-27 - 2026-COMMCON-0000183
11:00 AM - 01:00 PM: 112 - Frame
2026-05-26 - 2026-PLUMB-0001998
10:00 AM - 12:00 PM: 401 - Rough
10:00 AM - 12:00 PM: 403 - Pressure Test
2026-05-04 - 2026-PLUMB-0001998
08:30 AM - 10:30 AM: 400 - Groundwork
2026-04-29 - 2026-COMMCON-0000183
10:00 AM - 12:00 PM: 113 - Pre Construction Meeting
2026-04-08 - 2026-COMMCON-0000183
10:30 AM - 12:30 PM: 113 - Pre Construction Meeting