2026-10-27 - 2025-MECH-0008466
11:00 AM - 01:00 PM: 904 - Final - Mechanical
2026-10-27 - 2026-MECH-0001803
11:00 AM - 01:00 PM: 904 - Final - Mechanical
2026-10-26 - 2026-MECH-0001803
01:00 PM - 03:00 PM: Document Review
TBD: 904 - Final - Mechanical
2026-10-23 - 2025-ELEC-0009046
10:00 AM - 12:30 PM: 305 - Final - Electrical
2026-10-23 - 2025-MECH-0008466
08:30 AM - 10:30 AM: 904 - Final - Mechanical
2026-10-23 - 2026-ELEC-0003651
10:00 AM - 12:30 PM: 305 - Final - Electrical
2026-10-23 - 2026-MECH-0001803
08:30 AM - 10:30 AM: 904 - Final - Mechanical
2026-10-23 - 2026-PLUMB-0002551
10:00 AM - 12:00 PM: 402 - Final - Plumbing
2026-10-22 - 2025-ELEC-0009046
10:00 AM - 12:30 PM: 305 - Final - Electrical
2026-10-22 - 2026-ELEC-0003651
10:00 AM - 12:30 PM: 305 - Final - Electrical
2026-10-22 - 2026-PLUMB-0002551
10:00 AM - 12:00 PM: 402 - Final - Plumbing
2026-10-21 - 2026-FIRE-0004107
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-10-20 - 2026-ELEC-0003651
10:00 AM - 12:30 PM: 305 - Final - Electrical
2026-10-16 - 2026-FIRE-0004108
11:00 AM - 01:00 PM: 303 - Full Rough
2026-10-16 - 2026-ELEC-0003651
11:00 AM - 01:00 PM: 308 - Ceiling
2026-10-09 - 2026-ELEC-0003651
12:00 PM - 02:30 PM: 308 - Ceiling
2026-09-29 - 2026-ELEC-0003651
08:30 AM - 09:30 AM: 308 - Ceiling
2026-09-28 - 2025-PLUMB-0011280
08:00 AM - 10:00 AM: 401 - Rough
10:00 AM - 12:00 PM: 405 - Meter Release
2026-09-21 - 2025-MECH-0008466
01:00 PM - 03:00 PM: 903 - Rough
2026-09-10 - 2026-COMMCON-0000550
01:00 PM - 03:00 PM: 113 - Pre Construction Meeting
2026-09-09 - 2025-ELEC-0009046
08:30 AM - 10:30 AM: 307 - Service Equipment
08:30 AM - 10:30 AM: 313 - Meter Release
2026-09-09 - 2026-LOG-0004268
08:30 AM - 10:30 AM: 307 - Service Equipment
2026-09-08 - 2025-ELEC-0009046
12:00 PM - 02:30 PM: 307 - Service Equipment
12:00 PM - 02:30 PM: 313 - Meter Release
2026-09-04 - 2025-PLUMB-0011280
08:00 AM - 10:00 AM: 401 - Rough
2026-08-18 - 2026-ROOFSIDE-0003005
11:00 AM - 01:00 PM: 201 - Final - Roof
2026-08-18 - 2025-COMMCON-0001513
11:00 AM - 01:00 PM: 107 - Drywall
2026-08-14 - 2025-MECH-0008466
11:00 AM - 01:00 PM: 902 - Partial Rough
2026-08-13 - 2025-ELEC-0009046
08:30 AM - 09:30 AM: 308 - Ceiling
2026-07-20 - 2025-COMMCON-0001513
01:00 PM - 03:00 PM: 112 - Frame
2026-07-20 - 2025-PLUMB-0011280
08:00 AM - 10:00 AM: 401 - Rough
2026-07-10 - 2025-ELEC-0009046
08:30 AM - 09:30 AM: 309 - Walls
2026-07-07 - 2026-ROOFSIDE-0003005
12:30 PM - 02:30 PM: 201 - Final - Roof
2026-06-27 - 2026-ROOFSIDE-0003005
11:00 AM - 01:00 PM: 206 - Other
2026-06-26 - 2026-ROOFSIDE-0003005
11:00 AM - 01:00 PM: 206 - Other
2026-06-23 - 2026-ROOFSIDE-0003005
09:00 AM - 11:00 AM: 205 - Pre Inspection Commercial Flat Roof