2026-06-12 - 2025-RESCON-0003952
11:00 AM - 01:00 PM: 111 - Exterior Lath
2026-06-11 - 2026-MECH-0002861
01:00 PM - 03:00 PM: 903 - Rough
2026-06-10 - 2025-RESCON-0003952
11:00 AM - 01:00 PM: 111 - Exterior Lath
2026-06-04 - 2025-RESCON-0003952
01:00 PM - 03:00 PM: 105 - Exterior Sheathing
2026-05-27 - 2025-RESCON-0003952
11:00 AM - 01:00 PM: 107 - Drywall
2026-04-30 - 2025-RESCON-0003952
09:00 AM - 11:00 AM: 105 - Exterior Sheathing
2026-04-29 - 2025-RESCON-0003952
TBD: Document Review
2026-04-01 - 2025-RESCON-0003952
10:00 AM - 12:00 PM: 116 - Building Slab
2026-03-31 - 2025-RESCON-0003952
08:30 AM - 05:30 PM: 116 - Building Slab
2026-03-27 - 2026-PLUMB-0002709
08:30 AM - 11:30 AM: 400 - Groundwork
2026-02-18 - 2025-RESCON-0003952
TBD: 113 - Pre Construction Meeting
2026-02-13 - 2025-RESCON-0003951
11:00 AM - 01:00 PM: 108 - Final - Residential
11:00 AM - 01:00 PM: 109 - Other
2026-02-11 - 2025-RESCON-0003951
01:00 PM - 03:00 PM: 108 - Final - Residential
2026-01-15 - 2025-RESCON-0003951
11:00 AM - 01:00 PM: 113 - Pre Construction Meeting