2026-10-27 - 2026-MECH-0007061
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-10-13 - 2026-PLUMB-0008200
08:30 AM - 11:30 AM: 401 - Rough
2026-09-23 - 2026-RESCON-0001320
07:00 AM - 09:00 AM: Document Review
2026-09-09 - 2026-RESCON-0001320
09:00 AM - 11:00 AM: 105 - Exterior Sheathing
2026-09-03 - 2026-RESCON-0001320
08:30 AM - 05:30 PM: 105 - Exterior Sheathing
2026-08-05 - 2026-RESCON-0001320
11:00 AM - 01:00 PM: 103 - Waterproofing
2026-08-04 - 2026-MECH-0002744
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-07-30 - 2026-RESCON-0001320
12:00 PM - 02:00 PM: 101 - Foundation Wall
2026-07-23 - 2026-RESCON-0001320
10:00 AM - 12:00 PM: 100 - Footing
2026-06-25 - 2026-RESCON-0001320
12:00 PM - 02:00 PM: 113 - Pre Construction Meeting
2026-06-23 - 2026-RESCON-0001320
10:00 AM - 12:00 PM: 113 - Pre Construction Meeting