preloader

1799 N Pennsylvania St

Todays Alerts

1799 Pennsylvania St, Denver, CO 80203
Notify me if any times change for inspections listed under this address.

Notify me 30 minutes before the start time of this inspection.
2025-FIRE-0007555
08:00 AM - 10:30 AM: 302 - Partial Rough


2025-ELEC-0010553
08:00 AM - 10:30 AM: 302 - Partial Rough


2025-COMMCON-0001729
09:00 AM - 11:00 AM: 109 - Other


09:00 AM - 11:00 AM: 112 - Frame


Property Streetview
Property Map

Directions

  • 1799 Pennsylvania St, Denver, CO 80203, USA
  • Directions

Recently Scheduled Inspections

2026-10-27 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-10-27 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-10-27 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 109 - Other

09:00 AM - 11:00 AM: 112 - Frame

2026-10-26 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-23 - 2026-FIRE-0000659

10:00 AM - 12:00 PM: 411 - Rough

2026-10-23 - 2025-COMMCON-0001729

12:30 PM - 02:30 PM: 107 - Drywall

12:30 PM - 02:30 PM: 112 - Frame

2026-10-22 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-21 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-10-20 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-10-20 - 2025-MECH-0006177

11:00 AM - 01:00 PM: 903 - Rough

2026-10-19 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-16 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-10-15 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-10-13 - 2026-FIRE-0000659

08:00 AM - 11:00 AM: 411 - Rough

2026-10-13 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 112 - Frame

2026-10-09 - 2025-COMMCON-0001729

10:30 AM - 12:30 PM: 106 - Batt Insulation

10:30 AM - 12:30 PM: 112 - Frame

2026-10-08 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 112 - Frame

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-10-07 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 112 - Frame

2026-10-07 - 2025-ELEC-0010553

08:30 AM - 10:30 AM: 302 - Partial Rough

08:30 AM - 10:30 AM: 307 - Service Equipment

2026-10-06 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-05 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-02 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-10-01 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-09-30 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 112 - Frame

2026-09-29 - 2025-COMMCON-0001729

10:30 AM - 12:30 PM: 106 - Batt Insulation

10:30 AM - 12:30 PM: 112 - Frame

2026-09-28 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-09-25 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-09-24 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-09-23 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-09-22 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-21 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-18 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-09-18 - 2026-FIRE-0000659

10:00 AM - 12:00 PM: 411 - Rough

2026-09-18 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-18 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-09-17 - 2026-FIRE-0000659

08:15 AM - 10:15 AM: 411 - Rough

2026-09-17 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-16 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-09-16 - 2025-COMMCON-0001729

10:00 AM - 12:00 PM: 106 - Batt Insulation

10:00 AM - 12:00 PM: 107 - Drywall

10:00 AM - 12:00 PM: 112 - Frame

2026-09-16 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-09-15 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-14 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-11 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-10 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-09 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-08 - 2025-COMMCON-0001729

11:00 AM - 01:00 PM: 106 - Batt Insulation

11:00 AM - 01:00 PM: 107 - Drywall

11:00 AM - 01:00 PM: 112 - Frame

2026-09-04 - 2025-FIRE-0007555

08:30 AM - 05:30 PM: 302 - Partial Rough

2026-09-04 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-04 - 2025-ELEC-0010553

08:30 AM - 09:30 AM: 302 - Partial Rough

2026-09-03 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 112 - Frame

2026-09-02 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 112 - Frame

2026-09-02 - 2025-MECH-0006177

11:00 AM - 01:00 PM: 903 - Rough

2026-09-01 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-09-01 - 2026-FIRE-0000659

11:00 AM - 02:00 PM: 411 - Rough

2026-09-01 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-09-01 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-31 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-08-28 - 2025-COMMCON-0001729

12:00 PM - 02:00 PM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

09:00 AM - 11:00 AM: 112 - Frame

2026-08-28 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-28 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-27 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-27 - 2026-FIRE-0000659

11:00 AM - 02:00 PM: 411 - Rough

2026-08-27 - 2025-COMMCON-0001729

12:00 PM - 02:00 PM: 106 - Batt Insulation

12:00 PM - 02:00 PM: 107 - Drywall

12:00 PM - 02:00 PM: 112 - Frame

2026-08-27 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-26 - 2025-COMMCON-0001729

08:00 AM - 10:00 AM: 112 - Frame

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

2026-08-21 - 2026-FIRE-0000659

10:00 AM - 12:00 PM: 411 - Rough

2026-08-21 - 2025-COMMCON-0001729

11:00 AM - 01:00 PM: 106 - Batt Insulation

11:00 AM - 01:00 PM: 107 - Drywall

11:00 AM - 01:00 PM: 112 - Frame

2026-08-20 - 2025-FIRE-0007555

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-08-20 - 2026-FIRE-0000659

10:00 AM - 12:00 PM: 411 - Rough

2026-08-20 - 2025-COMMCON-0001729

11:00 AM - 01:00 PM: 112 - Frame

2026-08-20 - 2025-ELEC-0010553

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-08-19 - 2026-FIRE-0000659

12:00 PM - 02:00 PM: 411 - Rough

2026-08-19 - 2025-COMMCON-0001729

11:00 AM - 01:00 PM: 107 - Drywall

11:00 AM - 01:00 PM: 112 - Frame

2026-08-19 - 2025-PLUMB-0008276

12:00 PM - 02:00 PM: 401 - Rough

2026-08-18 - 2025-FIRE-0007555

08:30 AM - 05:30 PM: 302 - Partial Rough

2026-08-18 - 2026-FIRE-0000659

10:00 AM - 12:00 PM: 411 - Rough

2026-08-18 - 2025-ELEC-0010553

08:30 AM - 09:30 AM: 302 - Partial Rough

2026-08-18 - 2025-MECH-0006177

11:00 AM - 01:00 PM: 902 - Partial Rough

2026-08-15 - 2026-FIRE-0000659

TBD: 411 - Rough

2026-08-14 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-14 - 2025-COMMCON-0001729

12:00 PM - 02:00 PM: 107 - Drywall

2026-08-14 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-13 - 2025-COMMCON-0001729

08:30 AM - 09:30 AM: 107 - Drywall

2026-08-13 - 2025-PLUMB-0008276

08:30 AM - 09:30 AM: 401 - Rough

2026-08-12 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-12 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 107 - Drywall

2026-08-12 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-08-12 - 2025-MECH-0006177

11:00 AM - 01:00 PM: 903 - Rough

2026-08-11 - 2025-FIRE-0007555

08:30 AM - 10:30 AM: 302 - Partial Rough

2026-08-11 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-08-11 - 2025-ELEC-0010553

08:30 AM - 10:30 AM: 302 - Partial Rough

2026-08-10 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-08-10 - 2025-MECH-0006177

01:00 PM - 03:00 PM: 903 - Rough

2026-08-07 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-08-06 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-08-05 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-08-05 - 2025-MECH-0006177

11:00 AM - 01:00 PM: 903 - Rough

2026-08-04 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-31 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-30 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-30 - 2025-ELEC-0010553

09:00 AM - 11:00 AM: 302 - Partial Rough

2026-07-29 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-29 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-28 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-28 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-28 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-27 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-24 - 2025-FIRE-0007555

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-24 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-07-24 - 2025-ELEC-0010553

08:00 AM - 10:30 AM: 302 - Partial Rough

2026-07-23 - 2025-ELEC-0010553

12:00 PM - 02:00 PM: 302 - Partial Rough

2026-07-22 - 2025-FIRE-0007555

08:30 AM - 10:30 AM: 302 - Partial Rough

2026-07-22 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-07-22 - 2025-ELEC-0010553

08:30 AM - 10:30 AM: 302 - Partial Rough

2026-07-20 - 2025-FIRE-0007555

08:00 AM - 10:00 AM: 302 - Partial Rough

2026-07-20 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-20 - 2025-ELEC-0010553

08:00 AM - 10:00 AM: 303 - Full Rough

TBD: 302 - Partial Rough

2026-07-17 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-16 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-07-15 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-14 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-10 - 2025-MECH-0006177

09:00 AM - 11:00 AM: 903 - Rough

2026-07-09 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-08 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

2026-07-06 - 2025-MECH-0006177

09:00 AM - 11:00 AM: 903 - Rough

2026-07-06 - 2025-PLUMB-0008276

08:00 AM - 10:00 AM: 401 - Rough

2026-07-02 - 2025-COMMCON-0001729

09:30 AM - 11:30 AM: 107 - Drywall

2026-07-02 - 2025-PLUMB-0008276

08:30 AM - 09:30 AM: 401 - Rough

2026-07-01 - 2025-COMMCON-0001729

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 107 - Drywall

2026-06-30 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 106 - Batt Insulation

2026-06-29 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

2026-06-25 - 2025-COMMCON-0001729

10:00 AM - 01:00 PM: 106 - Batt Insulation

10:00 AM - 01:00 PM: 107 - Drywall

10:00 AM - 01:00 PM: 112 - Frame

2026-06-22 - 2025-COMMCON-0001729

08:29 AM - 10:30 AM: 106 - Batt Insulation

08:29 AM - 10:30 AM: 107 - Drywall

08:29 AM - 10:30 AM: 112 - Frame

User Login