2026-06-13 - 2026-COMMCON-0000809
11:00 AM - 01:00 PM: 113 - Pre Construction Meeting
2026-06-12 - 2026-COMMCON-0000809
11:00 AM - 01:00 PM: 113 - Pre Construction Meeting
2026-05-22 - 2025-COMMCON-0001688
01:00 PM - 03:00 PM: 108 - Final - Commercial
2026-05-20 - 2025-ELEC-0008466
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-05-20 - 2025-COMMCON-0001688
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-20 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-20 - 2025-ELEC-0010392
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-05-19 - 2025-ELEC-0008466
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-05-18 - 2025-COMMCON-0001688
01:00 PM - 03:00 PM: 108 - Final - Commercial
2026-05-18 - 2025-ELEC-0008466
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-05-18 - 2025-MECH-0005168
09:00 AM - 11:00 AM: 904 - Final - Mechanical
2026-05-18 - 2025-ELEC-0010392
TBD: 305 - Final - Electrical
2026-05-15 - 2025-FIRE-0006641
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-05-15 - 2025-COMMCON-0002554
01:00 PM - 03:00 PM: 108 - Final - Commercial
2026-05-14 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-14 - 2025-COMMCON-0002554
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-14 - 2025-ELEC-0010392
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-05-13 - 2026-FIRE-0001651
11:00 AM - 01:00 PM: 412 - Final - Fire Suppression
2026-05-13 - 2025-ELEC-0010392
08:30 AM - 10:30 AM: 305 - Final - Electrical
2026-05-12 - 2025-FIRE-0006641
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-05-12 - 2026-FIRE-0001651
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-05-08 - 2026-ACCCON-0000124
10:00 AM - 12:00 PM: 305 - Final - Access Control
2026-05-07 - 2025-COMMCON-0001813
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-07 - 2025-COMMCON-0002737
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-07 - 2025-MECH-0008178
TBD: Document Review
2026-05-07 - 2026-FIRE-0001651
11:00 AM - 01:00 PM: 412 - Final - Fire Suppression
2026-05-06 - 2025-MECH-0006486
09:00 AM - 11:00 AM: 904 - Final - Mechanical
2026-05-06 - 2025-MECH-0008178
09:00 AM - 11:00 AM: 904 - Final - Mechanical
2026-05-05 - 2026-FIRE-0000549
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-05-05 - 2025-COMMCON-0001813
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-05 - 2025-COMMCON-0002737
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-04 - 2025-COMMCON-0002737
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-05-04 - 2025-ELEC-0013218
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-05-01 - 2026-FIRE-0000495
01:00 PM - 03:00 PM: 412 - Final - Fire Suppression
2026-04-30 - 2025-FIRE-0006641
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-04-29 - 2025-ELEC-0013218
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-04-29 - 2026-PLUMB-0000423
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-04-28 - 2025-MECH-0008178
10:00 AM - 12:00 PM: 904 - Final - Mechanical
2026-04-24 - 2025-MECH-0006378
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-04-22 - 2025-ELEC-0013218
08:00 AM - 10:00 AM: 308 - Ceiling
2026-04-21 - 2025-COMMCON-0002554
11:00 AM - 01:00 PM: 107 - Drywall
2026-04-21 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 112 - Frame
2026-04-15 - 2025-COMMCON-0002554
11:30 AM - 01:30 PM: 109 - Other
2026-04-15 - 2025-ELEC-0013218
10:00 AM - 12:00 PM: 308 - Ceiling
2026-04-14 - 2025-COMMCON-0002062
01:00 PM - 03:00 PM: 108 - Final - Commercial
2026-04-13 - 2026-FIRE-0002010
08:00 AM - 10:00 AM: 303 - Full Rough
2026-04-10 - 2025-COMMCON-0002302
10:00 AM - 12:00 PM: 108 - Final - Commercial
2026-04-08 - 2026-FIRE-0000550
01:00 PM - 03:00 PM: 412 - Final - Fire Suppression
2026-04-08 - 2026-FIRE-0000812
01:00 PM - 03:00 PM: 412 - Final - Fire Suppression
2026-04-08 - 2025-ELEC-0011539
TBD: 305 - Final - Electrical
2026-04-08 - 2025-MECH-0008178
01:00 PM - 03:00 PM: 903 - Rough
2026-04-08 - 2025-MECH-0008653
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-04-07 - 2026-FIRE-0001651
08:00 AM - 10:00 AM: 411 - Rough
2026-04-07 - 2025-ELEC-0012134
09:00 AM - 11:00 AM: 305 - Final - Electrical
TBD: 307 - Service Equipment
2026-04-07 - 2025-ELEC-0013218
09:00 AM - 11:00 AM: 308 - Ceiling
2026-04-07 - 2025-PLUMB-0011032
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-04-06 - 2025-PLUMB-0011032
11:00 AM - 01:00 PM: 402 - Final - Plumbing
2026-04-03 - 2025-MECH-0008327
12:00 PM - 02:00 PM: 904 - Final - Mechanical
2026-04-03 - 2025-COMMCON-0002201
08:30 AM - 09:30 AM: 108 - Final - Commercial
2026-04-02 - 2025-COMMCON-0002302
12:00 PM - 02:00 PM: 112 - Frame
2026-04-02 - 2025-COMMCON-0002554
12:00 PM - 02:00 PM: 112 - Frame
2026-04-01 - 2026-COMMCON-0000082
01:00 PM - 03:00 PM: 109 - Other
2026-04-01 - 2025-COMMCON-0002201
01:00 PM - 03:00 PM: 109 - Other
2026-03-31 - 2025-COMMCON-0002302
12:00 PM - 02:00 PM: 112 - Frame
2026-03-31 - 2025-ELEC-0013218
09:00 AM - 11:00 AM: 301 - Underground
09:00 AM - 11:00 AM: 309 - Walls
2026-03-31 - 2026-COMMCON-0000082
12:00 PM - 02:00 PM: 109 - Other
2026-03-27 - 2025-ELEC-0012134
09:00 AM - 11:00 AM: 308 - Ceiling
2026-03-27 - 2026-MECH-0001579
12:00 PM - 02:00 PM: 904 - Final - Mechanical
2026-03-26 - 2025-ELEC-0011539
TBD: 302 - Partial Rough
TBD: 308 - Ceiling
2026-03-25 - 2025-COMMCON-0002302
01:00 PM - 03:00 PM: 112 - Frame
2026-03-25 - 2025-ELEC-0012134
09:00 AM - 11:00 AM: 308 - Ceiling
2026-03-25 - 2025-ELEC-0013996
09:00 AM - 11:00 AM: 308 - Ceiling
2026-03-25 - 2025-ELEC-0011539
TBD: 305 - Final - Electrical
TBD: 302 - Partial Rough
TBD: 308 - Ceiling
2026-03-24 - 2026-FIRE-0000550
08:00 AM - 10:00 AM: 411 - Rough
2026-03-24 - 2026-FIRE-0001049
09:00 AM - 11:00 AM: 303 - Full Rough
2026-03-24 - 2025-COMMCON-0001617
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-24 - 2025-ELEC-0012134
09:00 AM - 11:00 AM: 308 - Ceiling
2026-03-23 - 2025-FIRE-0006381
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-03-20 - 2025-FIRE-0006641
12:00 PM - 03:00 PM: 411 - Rough
2026-03-20 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 107 - Drywall
2026-03-20 - 2025-COMMCON-0002302
11:00 AM - 01:00 PM: 107 - Drywall
2026-03-20 - 2025-MECH-0008327
12:00 PM - 02:00 PM: 903 - Rough
2026-03-19 - 2025-FIRE-0006641
10:00 AM - 12:00 PM: 411 - Rough
2026-03-19 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 107 - Drywall
2026-03-18 - 2025-FIRE-0006381
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-03-18 - 2025-COMMCON-0001925
12:00 PM - 02:00 PM: 112 - Frame
2026-03-17 - 2025-COMMCON-0001617
11:00 AM - 01:00 PM: 112 - Frame
2026-03-16 - 2026-FIRE-0000495
12:30 PM - 02:30 PM: 411 - Rough
2026-03-16 - 2025-COMMCON-0002025
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-16 - 2025-ELEC-0008648
10:00 AM - 12:00 PM: 305 - Final - Electrical
10:00 AM - 12:00 PM: 308 - Ceiling
2026-03-13 - 2025-ELEC-0010392
09:00 AM - 11:00 AM: 308 - Ceiling
2026-03-13 - 2025-FIRE-0007480
09:00 AM - 11:00 AM: 303 - Full Rough
2026-03-13 - 2026-FIRE-0000306
09:00 AM - 11:00 AM: 303 - Full Rough
2026-03-13 - 2025-MECH-0008653
01:00 PM - 03:00 PM: 903 - Rough
2026-03-11 - 2025-COMMCON-0001617
11:00 AM - 01:00 PM: 112 - Frame
2026-03-11 - 2025-COMMCON-0002737
11:00 AM - 01:00 PM: 107 - Drywall
2026-03-11 - 2025-MECH-0008653
01:00 PM - 03:00 PM: 903 - Rough
2026-03-10 - 2025-COMMCON-0001730
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-10 - 2025-COMMCON-0002091
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-10 - 2025-COMMCON-0002737
01:00 PM - 03:00 PM: 107 - Drywall
01:00 PM - 03:00 PM: 112 - Frame
2026-03-09 - 2025-COMMCON-0002737
11:00 AM - 01:00 PM: 112 - Frame
2026-03-06 - 2025-COMMCON-0001349
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-06 - 2025-COMMCON-0002173
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-06 - 2025-COMMCON-0002753
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-06 - 2026-FIRE-0000495
10:30 AM - 01:00 PM: 411 - Rough
2026-03-06 - 2025-COMMCON-0002737
01:00 PM - 03:00 PM: 112 - Frame
2026-03-06 - 2025-ELEC-0010392
09:00 AM - 11:00 PM: 308 - Ceiling
2026-03-05 - 2025-FIRE-0007482
10:30 AM - 01:30 PM: 412 - Final - Fire Suppression
2026-03-05 - 2026-FIRE-0000125
10:30 AM - 01:30 PM: 412 - Final - Fire Suppression
2026-03-05 - 2026-FIRE-0000148
10:30 AM - 01:30 PM: 412 - Final - Fire Suppression
2026-03-05 - 2026-FIRE-0000495
10:30 AM - 01:30 PM: 412 - Final - Fire Suppression
2026-03-05 - 2025-COMMCON-0001349
11:00 AM - 01:00 PM: 108 - Final - Commercial
11:00 AM - 01:00 PM: 121 - Certificate of Occupancy
2026-03-05 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 112 - Frame
2026-03-05 - 2025-COMMCON-0002173
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-05 - 2025-COMMCON-0002753
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-03-04 - 2025-FIRE-0007482
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-04 - 2026-FIRE-0000125
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-04 - 2026-FIRE-0000148
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-04 - 2026-FIRE-0000495
08:30 AM - 05:30 PM: 411 - Rough
2026-03-04 - 2026-FIRE-0000549
08:30 AM - 05:30 PM: 412 - Final - Fire Suppression
2026-03-03 - 2025-FIRE-0005620
12:00 PM - 02:00 PM: 412 - Final - Fire Suppression
2026-03-03 - 2025-FIRE-0007482
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-03 - 2026-FIRE-0000125
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-03 - 2026-FIRE-0000148
09:00 AM - 11:00 AM: 412 - Final - Fire Suppression
2026-03-03 - 2025-FIRE-0006641
09:00 AM - 11:00 AM: 411 - Rough
2026-03-03 - 2025-MECH-0004948
09:00 AM - 11:00 AM: 904 - Final - Mechanical
2026-03-03 - 2026-COMMCON-0000082
08:30 AM - 09:30 AM: 108 - Final - Commercial
2026-03-02 - 2025-FIRE-0005620
12:00 PM - 02:00 PM: 412 - Final - Fire Suppression
2026-03-02 - 2025-FIRE-0007482
12:00 PM - 02:00 PM: 412 - Final - Fire Suppression
2026-03-02 - 2026-FIRE-0000125
12:00 PM - 02:00 PM: 412 - Final - Fire Suppression
2026-03-02 - 2026-FIRE-0000148
12:00 PM - 02:00 PM: 411 - Rough
12:00 PM - 02:00 PM: 412 - Final - Fire Suppression
2026-03-02 - 2025-COMMCON-0002737
10:30 AM - 12:30 PM: 112 - Frame
2026-03-02 - 2025-ELEC-0013996
08:30 AM - 10:30 AM: 308 - Ceiling
2026-03-02 - 2025-MECH-0004948
01:00 PM - 03:00 PM: 903 - Rough
2026-03-02 - 2026-FIRE-0000306
08:00 AM - 10:30 AM: 302 - Partial Rough
2026-02-27 - 2025-FIRE-0007480
08:00 AM - 10:00 AM: 303 - Full Rough
2026-02-27 - 2025-COMMCON-0001349
12:30 AM - 02:30 PM: 109 - Other
2026-02-27 - 2025-COMMCON-0001925
12:30 AM - 02:30 PM: 107 - Drywall
2026-02-27 - 2025-ELEC-0006646
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-27 - 2025-ELEC-0010392
08:00 AM - 10:00 AM: 308 - Ceiling
- TBD: 302 - Partial Rough
2026-02-27 - 2025-ELEC-0011205
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-27 - 2025-ELEC-0013964
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-27 - 2025-MECH-0006378
12:00 PM - 02:00 PM: 903 - Rough
2026-02-26 - 2025-COMMCON-0002201
10:30 AM - 12:30 PM: 108 - Final - Commercial
2026-02-26 - 2025-ELEC-0006646
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-02-26 - 2025-ELEC-0011205
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-02-26 - 2025-ELEC-0013964
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-02-26 - 2025-MECH-0004753
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-02-26 - 2025-PLUMB-0006682
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-26 - 2026-PLUMB-0000423
08:00 AM - 10:00 AM: 401 - Rough
2026-02-25 - 2025-BOILERAC-0001014
01:00 PM - 03:00 PM: 704 - Final - Boiler AC
2026-02-25 - 2025-FIRE-0005620
08:00 AM - 10:00 AM: 412 - Final - Fire Suppression
2026-02-25 - 2025-ELEC-0006646
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-25 - 2025-ELEC-0011205
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-25 - 2025-ELEC-0013964
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-25 - 2025-MECH-0004753
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-02-25 - 2025-MECH-0006759
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-02-25 - 2025-MECH-0008653
01:00 PM - 03:00 PM: 902 - Partial Rough
2026-02-25 - 2025-MECH-0008661
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-02-25 - 2025-PLUMB-0006682
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-25 - 2025-PLUMB-0009080
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-25 - 2025-PLUMB-0011573
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-24 - 2025-BOILERAC-0001014
08:00 AM - 11:00 AM: 701 - Pressure Test
2026-02-24 - 2025-MECH-0008661
08:00 AM - 11:00 AM: 903 - Rough
2026-02-23 - 2025-FIRE-0005620
11:00 AM - 01:00 PM: 411 - Rough
2026-02-23 - 2025-COMMCON-0002302
01:00 PM - 03:00 PM: 112 - Frame
2026-02-23 - 2025-ELEC-0006646
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-02-23 - 2025-ELEC-0013964
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-02-20 - 2025-FIRE-0005620
12:30 PM - 02:30 PM: 411 - Rough
2026-02-20 - 2025-ELEC-0006646
08:00 AM - 10:00 AM: 308 - Ceiling
2026-02-20 - 2025-ELEC-0011205
08:00 AM - 10:00 AM: 308 - Ceiling
2026-02-20 - 2025-ELEC-0013964
08:00 AM - 10:00 AM: 308 - Ceiling
2026-02-20 - 2026-ELEC-0000407
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-19 - 2025-FIRE-0006377
09:00 AM - 11:00 AM: 303 - Full Rough
2026-02-19 - 2025-COMMCON-0001925
01:00 PM - 03:00 PM: 112 - Frame
2026-02-19 - 2025-PLUMB-0011032
08:00 AM - 10:00 AM: 401 - Rough
2026-02-17 - 2026-FIRE-0000306
09:00 AM - 11:00 AM: 303 - Full Rough
2026-02-17 - 2025-COMMCON-0002737
01:00 PM - 03:00 PM: 112 - Frame
2026-02-17 - 2025-ELEC-0012134
09:00 AM - 11:00 AM: 303 - Full Rough
2026-02-17 - 2025-ELEC-0013996
09:00 AM - 11:00 AM: 308 - Ceiling
2026-02-17 - 2025-PLUMB-0008467
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-17 - 2025-PLUMB-0011032
08:00 AM - 10:00 AM: 401 - Rough
2026-02-13 - 2025-COMMCON-0001269
09:00 AM - 11:00 AM: 108 - Final - Commercial
2026-02-13 - 2025-ELEC-0010392
08:00 AM - 10:00 AM: 302 - Partial Rough
08:00 AM - 10:00 AM: 308 - Ceiling
08:00 AM - 10:00 AM: 309 - Walls
2026-02-12 - 2025-COMMCON-0002025
11:00 AM - 01:00 PM: 108 - Final - Commercial
2026-02-11 - 2025-COMMCON-0002025
12:00 PM - 02:00 PM: 108 - Final - Commercial
2026-02-11 - 2025-ELEC-0011507
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-02-10 - 2026-ELEC-0000407
08:00 AM - 10:00 AM: 302 - Partial Rough
2026-02-06 - 2025-COMMCON-0002737
01:00 PM - 03:00 PM: 113 - Pre Construction Meeting
2026-02-06 - 2025-ELEC-0011539
08:00 AM - 10:00 AM: 301 - Underground
08:00 AM - 10:00 AM: 309 - Walls
2026-02-06 - 2025-ELEC-0013996
08:00 AM - 10:00 AM: 301 - Underground
08:00 AM - 10:00 AM: 309 - Walls
2026-02-05 - 2025-COMMCON-0001925
11:00 AM - 01:00 PM: 112 - Frame
2026-02-05 - 2025-ELEC-0012134
08:00 AM - 10:00 AM: 301 - Underground
2026-02-05 - 2025-PLUMB-0011032
08:00 AM - 10:00 AM: 400 - Groundwork