2026-10-27 - 2025-RESCON-0000440
01:00 PM - 03:00 PM: 109 - Other
2026-10-22 - 2025-RESCON-0000440
11:00 AM - 01:00 PM: Document Review
11:00 AM - 01:00 PM: 109 - Other
11:00 AM - 01:00 PM: 200 - Blown Insulation
2026-10-21 - 2025-RESCON-0000440
09:00 AM - 11:00 AM: 113 - Pre Construction Meeting
2026-10-14 - 2026-ELEC-0002271
08:00 AM - 10:00 AM: 305 - Final - Electrical
2026-10-13 - 2026-ELEC-0002271
08:00 AM - 10:00 AM: 305 - Final - Electrical
08:00 AM - 10:00 AM: 307 - Service Equipment
08:30 AM - 09:30 AM: 313 - Meter Release
2026-10-10 - 2026-ELEC-0001369
10:00 AM - 12:00 PM: 305 - Final - Electrical
2026-10-09 - 2026-ELEC-0001369
10:00 AM - 12:00 PM: 305 - Final - Electrical
2026-10-07 - 2025-MECH-0008296
12:00 PM - 02:00 PM: Document Review
2026-10-06 - 2025-MECH-0008296
12:00 PM - 02:00 PM: 904 - Final - Mechanical
2026-10-06 - 2025-PLUMB-0008703
01:00 PM - 03:00 PM: 402 - Final - Plumbing
2026-10-06 - 2026-MECH-0000152
12:00 PM - 02:00 PM: 904 - Final - Mechanical
2026-08-31 - 2026-MECH-0004394
11:00 AM - 01:00 PM: 904 - Final - Mechanical
2026-07-20 - 2026-MECH-0004394
12:00 PM - 02:00 PM: 901 - Pressure Test
2026-07-14 - 2025-ROOFSIDE-0010367
09:00 AM - 11:00 PM: 201 - Final - Roof
2026-07-14 - 2025-ROOFSIDE-0010368
09:00 AM - 11:00 PM: 201 - Final - Roof