Recently Scheduled Inspections

2026-06-12 - 2024-COMMCON-0002739

12:00 PM - 02:00 PM: 112 - Frame

2026-06-08 - 2024-COMMCON-0002739

10:00 AM - 12:00 PM: 112 - Frame

2026-06-05 - 2024-COMMCON-0002739

10:00 AM - 12:00 PM: 112 - Frame

2026-06-03 - 2025-FIRE-0006874

12:00 PM - 02:30 PM: 302 - Partial Rough

2026-06-03 - 2025-ELEC-0002535

12:00 PM - 02:30 PM: 302 - Partial Rough

2026-05-27 - 2024-COMMCON-0002739

09:30 AM - 11:30 AM: 107 - Drywall

09:30 AM - 11:30 AM: 112 - Frame

2026-05-22 - 2024-COMMCON-0002739

01:00 PM - 03:00 PM: 107 - Drywall

2026-05-21 - 2025-FIRE-0005297

10:30 AM - 12:30 PM: 411 - Rough

2026-05-21 - 2025-FIRE-0006874

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-05-21 - 2025-ELEC-0002535

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-05-20 - 2025-ELEC-0002535

08:30 AM - 10:30 AM: 303 - Full Rough

2026-05-18 - 2024-COMMCON-0002739

11:00 AM - 01:00 PM: 105 - Exterior Sheathing

11:00 AM - 01:00 PM: 107 - Drywall

2026-05-18 - 2025-FIRE-0005297

10:30 AM - 12:30 PM: 411 - Rough

2026-05-15 - 2025-ELEC-0002535

08:00 AM - 10:00 AM: 303 - Full Rough

2026-05-15 - 2025-FIRE-0006874

08:00 AM - 10:00 AM: 302 - Partial Rough

2026-05-14 - 2025-FIRE-0005297

08:00 AM - 10:00 PM: 411 - Rough

2026-05-13 - 2025-FIRE-0005297

08:15 AM - 10:15 AM: 411 - Rough

2026-05-12 - 2025-FIRE-0005297

TBD: 411 - Rough

2026-05-11 - 2025-FIRE-0005297

08:15 AM - 10:15 AM: 411 - Rough

2026-05-09 - 2025-FIRE-0005297

01:00 PM - 03:00 PM: 411 - Rough

2026-05-08 - 2025-FIRE-0005297

01:00 PM - 03:00 PM: 411 - Rough

2026-05-04 - 2024-COMMCON-0002739

12:00 PM - 02:00 PM: 112 - Frame

2026-05-01 - 2025-PLUMB-0003741

08:30 AM - 10:30 AM: 401 - Rough

2026-04-30 - 2025-PLUMB-0003742

08:00 AM - 10:00 AM: 401 - Rough

2026-04-23 - 2025-MECH-0002348

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-04-21 - 2024-COMMCON-0002739

10:00 AM - 12:00 PM: 107 - Drywall

2026-04-17 - 2025-COMMCON-0000826

TBD: 108 - Final - Commercial

2026-04-16 - 2025-COMMCON-0000826

10:00 AM - 12:00 PM: 121 - Certificate of Occupancy

2026-04-16 - 2025-PLUMB-0003741

10:15 AM - 12:30 PM: 401 - Rough

2026-04-15 - 2025-PLUMB-0003742

10:15 AM - 12:15 PM: 403 - Pressure Test

2026-04-06 - 2024-COMMCON-0002739

10:00 AM - 12:00 PM: 105 - Exterior Sheathing

2026-04-06 - 2025-ELEC-0002535

08:30 AM - 10:30 AM: 303 - Full Rough

2026-04-06 - 2025-FIRE-0006874

TBD: 302 - Partial Rough

2026-03-31 - 2025-COMMCON-0000826

09:30 AM - 11:30 AM: 109 - Other

2026-03-27 - 2025-COMMCON-0000826

12:00 PM - 02:00 PM: 113 - Pre Construction Meeting

2026-03-26 - 2025-COMMCON-0002106

10:00 AM - 12:00 PM: 108 - Final - Commercial

2026-03-26 - 2025-COMMCON-0000826

10:00 AM - 12:00 PM: 120 - Temporary Certificate of Occupancy

2026-03-25 - 2025-COMMCON-0002106

10:00 AM - 12:00 PM: 108 - Final - Commercial

2026-03-23 - 2025-ROOFSIDE-0009352

09:00 AM - 11:00 AM: 201 - Final - Roof

2026-03-23 - 2025-COMMCON-0000826

09:00 AM - 11:00 AM: 108 - Final - Commercial

2026-03-23 - 2026-COMMCON-0000149

09:00 AM - 11:00 AM: 108 - Final - Commercial

2026-03-20 - 2025-COMMCON-0000826

09:30 AM - 11:30 AM: 109 - Other

2026-03-19 - 2025-COMMCON-0000826

01:30 PM - 03:00 PM: 108 - Final - Commercial

2026-03-19 - 2025-ELEC-0007356

12:00 PM - 02:30 PM: 305 - Final - Electrical

2026-03-18 - 2025-FIRE-0006883

08:15 AM - 10:15 AM: 412 - Final - Fire Suppression

2026-03-18 - 2024-COMMCON-0002739

09:30 AM - 11:30 AM: 112 - Frame

2026-03-18 - 2025-PLUMB-0003741

08:15 AM - 10:15 AM: 403 - Pressure Test

2026-03-13 - 2026-ELEC-0001150

- TBD: 305 - Final - Electrical

2026-03-13 - 2025-ELEC-0007356

08:30 AM - 10:30 AM: 305 - Final - Electrical

2026-03-13 - 2025-PLUMB-0003741

10:15 AM - 12:15 PM: 403 - Pressure Test

2026-03-13 - 2024-COMMCON-0002739

10:30 AM - 12:30 PM: 112 - Frame

2026-03-11 - 2025-ELEC-0007356

08:00 AM - 10:00 AM: 304 - Partial Final

2026-03-11 - 2025-BOILERAC-0000489

11:00 AM - 01:00 PM: 704 - Final - Boiler AC

2026-03-11 - 2025-MECH-0003801

01:00 PM - 03:00 PM: 904 - Final - Mechanical

2026-03-10 - 2025-MECH-0003801

01:00 PM - 03:00 PM: 904 - Final - Mechanical

2026-03-09 - 2025-PLUMB-0003741

08:15 AM - 10:30 AM: 403 - Pressure Test

2026-03-06 - 2025-COMMCON-0002106

11:00 AM - 01:00 PM: 113 - Pre Construction Meeting

2026-03-06 - 2025-PLUMB-0005720

08:00 AM - 01:00 PM: 402 - Final - Plumbing

2026-03-06 - 2026-PLUMB-0000782

08:00 AM - 01:00 PM: 402 - Final - Plumbing

2026-03-05 - 2026-COMMCON-0000149

TBD: 113 - Pre Construction Meeting