2026-10-27 - 2026-ELEC-0005604
09:00 AM - 11:00 AM: 305 - Final - Electrical
09:00 AM - 11:00 AM: 307 - Service Equipment
09:00 AM - 11:00 AM: 313 - Meter Release
2026-10-27 - 2026-PLUMB-0004845
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-08-07 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 107 - Drywall
2026-08-06 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 107 - Drywall
2026-07-30 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 106 - Batt Insulation
09:00 AM - 11:00 AM: 112 - Frame
2026-07-28 - 2026-ROOFSIDE-0002923
09:00 AM - 11:00 AM: 201 - Final - Roof
2026-07-15 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 106 - Batt Insulation
01:00 PM - 03:00 PM: 112 - Frame
2026-07-10 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 112 - Frame
2026-07-08 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 112 - Frame
2026-07-06 - 2026-MECH-0004042
11:00 AM - 01:00 PM: 904 - Final - Mechanical
2026-07-02 - 2026-ELEC-0005604
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-07-01 - 2026-ELEC-0005604
01:00 PM - 03:00 PM: 305 - Final - Electrical
TBD: 307 - Service Equipment
TBD: 313 - Meter Release
2026-06-29 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 113 - Pre Construction Meeting
2026-06-26 - 2026-PLUMB-0004845
01:00 PM - 03:00 PM: 401 - Rough
01:00 PM - 03:00 PM: 403 - Pressure Test
2026-06-26 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 113 - Pre Construction Meeting
2026-06-25 - 2026-PLUMB-0004845
01:00 PM - 03:00 PM: 401 - Rough
01:00 PM - 03:00 PM: 403 - Pressure Test
2026-06-23 - 2026-RESCON-0001176
08:30 AM - 05:30 PM: 113 - Pre Construction Meeting