2026-03-02 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-02-27 - 2025-FIRE-0006826
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-02-27 - 2025-ELEC-0001927
08:30 AM - 10:30 AM: 303 - Full Rough
08:30 AM - 10:30 AM: 304 - Partial Final
2026-02-26 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
2026-02-26 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 902 - Partial Rough
2026-02-26 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-02-24 - 2024-COMMCON-0002697
08:30 AM - 09:30 AM: 107 - Drywall
08:30 AM - 09:30 AM: 108 - Final - Commercial
08:30 AM - 09:30 AM: 112 - Frame
2026-02-24 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-23 - 2025-FIRE-0006826
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-02-23 - 2025-ELEC-0001927
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-02-23 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-02-20 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 302 - Partial Rough
07:30 AM - 09:30 AM: 304 - Partial Final
2026-02-20 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-19 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 106 - Batt Insulation
09:00 AM - 11:00 AM: 112 - Frame
2026-02-19 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-02-18 - 2025-FIRE-0006324
08:00 AM - 10:00 AM: 411 - Rough
2026-02-18 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 903 - Rough
2026-02-18 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-17 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-02-17 - 2025-MECH-0000594
08:30 AM - 09:30 AM: 903 - Rough
2026-02-13 - 2025-FIRE-0006826
07:30 AM - 09:30 AM: 302 - Partial Rough
2026-02-13 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 108 - Final - Commercial
09:00 AM - 11:00 AM: 112 - Frame
2026-02-13 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 302 - Partial Rough
07:30 AM - 09:30 AM: 304 - Partial Final
2026-02-13 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-02-12 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 108 - Final - Commercial
09:00 AM - 11:00 AM: 112 - Frame
2026-02-12 - 2025-PLUMB-0000851
10:30 AM - 12:30 PM: 402 - Final - Plumbing
2026-02-11 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-02-11 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 903 - Rough
2026-02-06 - 2025-PLUMB-0000851
08:30 AM - 10:30 AM: 401 - Rough
2026-02-05 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 108 - Final - Commercial
2026-02-05 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 302 - Partial Rough
07:30 AM - 09:30 AM: 304 - Partial Final
2026-02-05 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-02-04 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
11:00 AM - 01:00 PM: 112 - Frame
2026-02-04 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 903 - Rough
2026-02-04 - 2025-PLUMB-0000851
08:15 AM - 10:30 AM: 401 - Rough
2026-02-03 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 106 - Batt Insulation
2026-01-30 - 2025-FIRE-0006334
07:30 AM - 09:30 AM: 302 - Partial Rough
2026-01-30 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-01-30 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 302 - Partial Rough
2026-01-29 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 302 - Partial Rough
2026-01-29 - 2025-FIRE-0006826
07:30 AM - 09:30 AM: 302 - Partial Rough
2026-01-29 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-01-29 - 2024-COMMCON-0002697
08:29 AM - 10:30 AM: 108 - Final - Commercial
08:29 AM - 10:30 AM: 112 - Frame
2026-01-28 - 2025-FIRE-0006324
08:00 AM - 10:00 AM: 411 - Rough
2026-01-28 - 2025-FIRE-0006826
08:00 AM - 10:00 AM: 302 - Partial Rough
2026-01-28 - 2025-ELEC-0001927
08:00 AM - 10:00 AM: 302 - Partial Rough
2026-01-28 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 903 - Rough
2026-01-28 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-01-27 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
2026-01-26 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-01-26 - 2025-PLUMB-0000851
08:15 AM - 10:15 AM: 401 - Rough
2026-01-22 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 401 - Rough
2026-01-22 - 2025-MECH-0000594
08:00 AM - 11:00 AM: 903 - Rough
2026-01-22 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 112 - Frame
2026-01-21 - 2025-PLUMB-0011559
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-01-20 - 2025-PLUMB-0011559
08:00 AM - 10:00 AM: 400 - Groundwork
2026-01-16 - 2024-COMMCON-0002697
09:00 AM - 11:00 AM: 106 - Batt Insulation
2026-01-15 - 2025-ELEC-0001927
07:30 AM - 09:30 AM: 304 - Partial Final
2026-01-15 - 2025-PLUMB-0000851
08:00 AM - 10:00 AM: 402 - Final - Plumbing