Recent Inspections

2026-06-12 - 2026-MECH-0002549

01:00 PM - 03:00 PM: 903 - Rough

2026-06-10 - 2026-MECH-0002549

01:00 PM - 03:00 PM: 903 - Rough

2026-06-09 - 2026-PLUMB-0003680

08:00 AM - 10:00 AM: 401 - Rough

2026-06-04 - 2026-PLUMB-0003680

08:00 AM - 10:00 AM: 401 - Rough

2026-06-03 - 2026-ELEC-0003732

08:30 AM - 10:30 AM: 303 - Full Rough

2026-06-03 - 2026-PLUMB-0003680

12:00 PM - 03:00 PM: 401 - Rough

2026-06-02 - 2026-PLUMB-0003680

10:00 AM - 12:00 PM: 401 - Rough

2026-05-20 - 2026-PLUMB-0003680

10:00 AM - 12:00 PM: 401 - Rough

3301 N Valentia ST

Directions

Recent Inspections

2026-06-12 - 2024-ROOFSIDE-0005881

10:00 AM - 12:00 PM: 201 - Final - Roof

2026-06-11 - 2024-ROOFSIDE-0005881

11:30 AM - 01:30 PM: 201 - Final - Roof

2026-05-19 - 2026-ELEC-0002941

08:30 AM - 10:30 AM: 307 - Service Equipment

08:30 AM - 10:30 AM: 305 - Final - Electrical

2026-05-19 - 2026-MECH-0002000

09:00 AM - 11:00 AM: 904 - Final - Mechanical

3200 Larimer ST

Directions

Recent Inspections

2026-06-12 - 2026-ELEC-0002170

10:00 AM - 12:30 PM: 301 - Underground

2026-06-08 - 2026-PLUMB-0002326

11:00 AM - 02:00 PM: 400 - Groundwork

2026-06-02 - 2026-ELEC-0002170

08:00 AM - 10:30 AM: 301 - Underground

2026-05-28 - 2026-ELEC-0002170

12:00 PM - 02:00 PM: 301 - Underground

2026-05-19 - 2026-COMMCON-0000130

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2313 N Alton St

Directions

Recent Inspections

2026-06-12 - 2026-MECH-0003115

11:00 AM - 01:00 PM: 903 - Rough

2026-06-10 - 2026-PLUMB-0004837

09:00 AM - 11:00 AM: 401 - Rough

2026-06-09 - 2026-RESCON-0001692

10:00 AM - 12:00 PM: 113 - Pre Construction Meeting

2026-06-04 - 2026-RESCON-0000870

08:30 AM - 05:30 PM: 105 - Exterior Sheathing

2026-06-03 - 2026-RESCON-0000870

10:00 AM - 12:00 PM: 105 - Exterior Sheathing

2026-06-02 - 2026-RESCON-0000870

09:30 AM - 11:30 AM: 105 - Exterior Sheathing

2026-05-15 - 2026-RESCON-0000870

09:30 AM - 11:30 AM: 113 - Pre Construction Meeting

1750 S Federal BLVD

Directions

Recent Inspections

2026-06-13 - 2026-FIRE-0002930

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-06-12 - 2026-FIRE-0002930

08:30 AM - 05:30 PM: 412 - Final - Fire Suppression

2026-06-11 - 2026-FIRE-0002930

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-06-10 - 2026-FIRE-0002930

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-06-09 - 2026-FIRE-0002930

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-06-08 - 2026-FIRE-0002930

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-06-06 - 2026-FIRE-0002930

11:00 AM - 03:00 PM: 411 - Rough

2026-06-05 - 2026-FIRE-0002930

11:00 AM - 03:00 PM: 411 - Rough

2026-05-15 - 2025-FIRE-0007225

10:00 AM - 12:00 PM: 410 - Underground

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-05-14 - 2025-FIRE-0007225

10:00 AM - 12:00 PM: 410 - Underground

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2268 N Birch ST

Directions

Recent Inspections

2026-06-12 - 2026-RESCON-0000810

10:00 AM - 01:00 PM: 105 - Exterior Sheathing

2026-06-03 - 2026-PLUMB-0004594

12:00 PM - 03:00 PM: 400 - Groundwork

2026-05-22 - 2026-RESCON-0000810

09:30 AM - 11:30 AM: 101 - Foundation Wall

2026-05-18 - 2026-RESCON-0000810

10:00 AM - 12:00 PM: 100 - Footing

2026-05-14 - 2026-RESCON-0000810

10:00 AM - 12:00 PM: 113 - Pre Construction Meeting

5341 N Granby ST

Directions

Recent Inspections

2026-06-12 - 2026-RESCON-0001575

11:00 AM - 01:00 PM: 108 - Final - Residential

2026-06-10 - 2026-RESCON-0001575

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2026-06-05 - 2025-FIRE-0006930

09:00 AM - 11:00 AM: 303 - Full Rough

2026-06-04 - 2026-PLUMB-0004333

08:00 AM - 10:30 AM: 401 - Rough

2026-05-29 - 2025-FIRE-0006930

08:30 AM - 10:30 AM: 303 - Full Rough

2026-05-08 - 2026-FIRE-0001618

08:00 AM - 11:00 AM: 411 - Rough

3685 W 16th

Directions

Recent Inspections

2026-06-12 - 2025-FIRE-0005174

01:00 PM - 03:00 PM: 303 - Full Rough

2026-06-11 - 2023-BOILERAC-0000180

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-06-11 - 2023-MECH-0002075

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-06-11 - 2023-PLUMB-0001978

09:00 AM - 11:00 AM: 402 - Final - Plumbing

2026-06-10 - 2022-COMMCON-0001924

10:00 AM - 12:00 PM: 109 - Other

2026-06-02 - 2022-COMMCON-0001924

TBD: Document Review Inspection

01:00 PM - 03:00 PM: 107 - Drywall

01:00 PM - 03:00 PM: 112 - Frame

2026-06-01 - 2022-COMMCON-0001924

12:30 PM - 02:30 PM: 107 - Drywall

12:30 PM - 02:30 PM: 109 - Other

2026-05-29 - 2022-COMMCON-0001924

09:00 AM - 11:00 AM: 107 - Drywall

2026-05-28 - 2022-COMMCON-0001924

12:00 PM - 02:00 PM: 106 - Batt Insulation

12:00 PM - 02:00 PM: 107 - Drywall

12:00 PM - 02:00 PM: 109 - Other

2026-05-27 - 2022-COMMCON-0001924

12:00 PM - 02:00 PM: 107 - Drywall

12:00 PM - 02:00 PM: 112 - Frame

2026-05-26 - 2022-COMMCON-0001924

10:00 AM - 12:00 PM: 106 - Batt Insulation

10:00 AM - 12:00 PM: 109 - Other

10:00 AM - 12:00 PM: 112 - Frame

2026-05-22 - 2022-COMMCON-0001924

11:00 AM - 01:00 PM: 112 - Frame

2026-05-21 - 2022-COMMCON-0001924

12:00 PM - 02:00 PM: 106 - Batt Insulation

2026-05-20 - 2022-COMMCON-0001924

11:00 AM - 01:00 PM: 112 - Frame

2026-05-19 - 2022-COMMCON-0001924

12:00 PM - 02:00 PM: 109 - Other

2026-05-14 - 2022-COMMCON-0001924

10:00 AM - 12:00 PM: 107 - Drywall

2026-05-13 - 2023-PLUMB-0001978

11:00 AM - 01:00 PM: 403 - Pressure Test

2026-05-12 - 2022-COMMCON-0001924

11:00 AM - 01:00 PM: 107 - Drywall

11:00 AM - 01:00 PM: 112 - Frame

2026-05-08 - 2023-PLUMB-0001978

08:00 AM - 11:00 AM: 401 - Rough

2777 Mile High Stadium CIR

Directions

Recent Inspections

2026-06-12 - 2026-PLUMB-0002203

10:00 AM - 12:00 PM: 401 - Rough

2026-06-11 - 2026-ELEC-0002114

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-06-10 - 2026-COMMCON-0000451

01:00 PM - 03:00 PM: 106 - Batt Insulation

01:00 PM - 03:00 PM: 107 - Drywall

2026-06-09 - 2026-COMMCON-0000451

10:30 AM - 12:30 PM: 106 - Batt Insulation

10:30 AM - 12:30 PM: 112 - Frame

2026-06-09 - 2026-ELEC-0002129

11:00 AM - 01:00 PM: 301 - Underground

2026-06-08 - 2026-COMMCON-0000451

08:30 AM - 09:30 AM: 107 - Drywall

2026-06-08 - 2026-ELEC-0002129

11:00 AM - 01:00 PM: 302 - Partial Rough

2026-06-05 - 2026-PLUMB-0002197

08:00 AM - 11:00 AM: 401 - Rough

2026-06-04 - 2026-COMMCON-0000451

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 112 - Frame

2026-06-03 - 2026-COMMCON-0000451

01:00 PM - 03:00 PM: 107 - Drywall

2026-06-02 - 2026-COMMCON-0000451

01:00 PM - 03:00 PM: 107 - Drywall

2026-06-01 - 2026-ELEC-0002114

11:00 AM - 01:00 PM: 302 - Partial Rough

2026-05-29 - 2026-PLUMB-0002197

08:00 AM - 10:00 AM: 401 - Rough

2026-05-28 - 2026-COMMCON-0000451

09:00 AM - 11:00 AM: 106 - Batt Insulation

2026-05-21 - 2026-COMMCON-0000451

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 112 - Frame

2026-05-20 - 2026-COMMCON-0000451

12:00 PM - 02:00 PM: 112 - Frame

2026-05-20 - 2026-PLUMB-0003783

09:00 AM - 11:00 AM: 402 - Final - Plumbing

2026-05-19 - 2026-COMMCON-0000451

01:00 PM - 03:00 PM: 109 - Other

2026-05-19 - 2026-ELEC-0002114

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-05-15 - 2026-COMMCON-0000451

10:00 AM - 12:00 PM: 106 - Batt Insulation

2026-05-14 - 2026-COMMCON-0000451

11:00 AM - 01:00 PM: 106 - Batt Insulation

11:00 AM - 01:00 PM: 112 - Frame

2026-05-14 - 2026-PLUMB-0002203

09:00 AM - 11:00 AM: 400 - Groundwork

2026-05-13 - 2026-COMMCON-0000451

11:00 AM - 01:00 PM: 106 - Batt Insulation

11:00 AM - 01:00 PM: 112 - Frame

2026-05-12 - 2026-COMMCON-0000451

09:00 AM - 11:00 AM: 106 - Batt Insulation

09:00 AM - 11:00 AM: 112 - Frame

2026-05-12 - 2026-ELEC-0002114

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-05-12 - 2026-ELEC-0002129

01:00 PM - 03:00 PM: 301 - Underground

2026-05-11 - 2026-COMMCON-0000451

12:30 PM - 02:30 PM: 112 - Frame

2026-05-11 - 2026-PLUMB-0002197

11:00 AM - 01:00 PM: 401 - Rough

2026-05-08 - 2026-COMMCON-0000451

01:00 PM - 03:00 PM: 113 - Pre Construction Meeting

2026-05-08 - 2026-ELEC-0002114

11:00 AM - 01:00 PM: 302 - Partial Rough

920 N Ogden ST

Directions

Recent Inspections

2026-06-12 - 2026-PLUMB-0004938

10:00 AM - 01:00 PM: 402 - Final - Plumbing

2026-06-09 - 2025-RESCON-0002816

09:00 AM - 11:00 AM: 100 - Footing

09:00 AM - 11:00 AM: 101 - Foundation Wall

09:00 AM - 11:00 AM: 103 - Waterproofing

09:00 AM - 11:00 AM: 109 - Other

2026-05-19 - 2025-RESCON-0002816

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2026-05-18 - 2025-RESCON-0002816

08:29 AM - 10:30 AM: 113 - Pre Construction Meeting

2026-05-15 - 2025-RESCON-0002816

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2026-05-08 - 2025-RESCON-0002816

08:29 AM - 10:30 AM: 113 - Pre Construction Meeting