1699 S Colorado BLVD
Recent Inspections
2026-09-11 - 2026-PLUMB-0007431
08:30 AM - 11:30 AM: 402 - Final - Plumbing
2026-09-04 - 2026-COMMCON-0000922
09:00 AM - 11:00 AM: 112 - Frame
2026-08-14 - 2026-FIRE-0004132
08:30 AM - 11:30 AM: 411 - Rough
2026-08-14 - 2026-ELEC-0004419
11:00 AM - 01:00 PM: 302 - Partial Rough
2026-08-03 - 2026-ELEC-0004419
08:30 AM - 09:30 AM: 309 - Walls
1234 S Beach CT
Recent Inspections
2026-09-11 - 2026-ELEC-0007918
01:00 PM - 03:00 PM: 307 - Service Equipment
01:00 PM - 03:00 PM: 313 - Meter Release
2026-09-11 - 2026-ELEC-0007920
01:00 PM - 03:00 PM: 305 - Final - Electrical
2026-08-31 - 2026-RESCON-0002135
11:00 AM - 01:00 PM: 105 - Exterior Sheathing
11:00 AM - 01:00 PM: 107 - Drywall
12:00 PM - 02:00 PM: 112 - Frame
2026-08-29 - 2026-RESCON-0002135
10:00 AM - 12:00 PM: 109 - Other
2026-08-28 - 2026-RESCON-0002135
10:00 AM - 12:00 PM: Document Review
10:00 AM - 12:00 PM: 109 - Other
2026-08-03 - 2026-RESCON-0002135
11:00 AM - 01:00 PM: 113 - Pre Construction Meeting
801 W 8th AVE
Recent Inspections
2026-09-11 - 2026-ELEC-0006132
09:00 AM - 11:00 AM: 307 - Service Equipment
09:00 AM - 11:00 AM: 313 - Meter Release
2026-09-11 - 2026-ELEC-0007905
09:00 AM - 11:00 AM: 313 - Meter Release
2026-09-10 - 2026-ELEC-0007905
09:00 AM - 11:00 AM: 313 - Meter Release
2026-09-10 - 2026-ELEC-0006132
09:00 AM - 11:00 AM: 307 - Service Equipment
09:00 AM - 11:00 AM: 313 - Meter Release
2026-09-09 - 2026-ELEC-0007905
08:30 AM - 09:30 AM: 313 - Meter Release
2026-09-02 - 2026-MECH-0004143
09:00 AM - 11:00 AM: 903 - Rough
2026-08-28 - 2026-ELEC-0007905
09:00 AM - 11:00 AM: 313 - Meter Release
2026-08-19 - 2026-COMMCON-0001325
10:00 AM - 12:00 PM: 113 - Pre Construction Meeting
2026-08-19 - 2026-ELEC-0006132
10:00 AM - 12:00 PM: 313 - Meter Release
TBD: 307 - Service Equipment
2026-07-31 - 2026-PLUMB-0005876
08:00 AM - 10:00 AM: 400 - Groundwork
7535 E Hampden AVE
Recent Inspections
2026-09-11 - 2026-PLUMB-0004841
08:30 AM - 11:30 AM: 402 - Final - Plumbing
2026-09-09 - 2026-MECH-0003421
TBD: Document Review
2026-09-09 - 2026-ELEC-0005157
12:00 PM - 02:00 PM: 305 - Final - Electrical
2026-09-03 - 2026-ELEC-0005157
10:00 AM - 12:00 PM: 305 - Final - Electrical
2026-09-02 - 2026-ELEC-0005157
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-08-27 - 2026-ELEC-0005157
11:00 AM - 01:00 PM: 308 - Ceiling
2026-08-27 - 2026-MECH-0003421
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-07-31 - 2026-ELEC-0005157
12:00 PM - 02:00 PM: 309 - Walls
2026-07-30 - 2026-COMMCON-0001136
11:00 AM - 01:00 PM: 112 - Frame
2026-07-30 - 2026-ELEC-0005157
08:30 AM - 09:30 AM: 309 - Walls
2026-07-29 - 2026-PLUMB-0004841
09:30 AM - 12:30 PM: 401 - Rough
432 N Columbine ST
Recent Inspections
2026-09-11 - 2026-RESCON-0002238
11:00 AM - 01:00 PM: 107 - Drywall
2026-09-09 - 2026-RESCON-0002238
09:00 AM - 11:00 AM: 112 - Frame
2026-09-09 - 2026-MECH-0005811
12:00 PM - 02:00 PM: 903 - Rough
2026-09-08 - 2026-RESCON-0002238
09:00 AM - 11:00 AM: 112 - Frame
2026-09-01 - 2026-RESCON-0002238
11:00 AM - 01:00 PM: 112 - Frame
2026-08-31 - 2026-PLUMB-0007065
10:00 AM - 12:00 PM: 401 - Rough
2026-08-03 - 2026-ELEC-0006999
10:00 AM - 12:00 PM: 313 - Meter Release
TBD: 305 - Final - Electrical
TBD: 307 - Service Equipment
2026-07-29 - 2026-RESCON-0002238
11:00 AM - 01:00 PM: 113 - Pre Construction Meeting
3647 N Mariposa ST
Recent Inspections
2026-09-11 - 2026-ROOFSIDE-0004615
08:30 AM - 10:30 AM: 205 - Pre Inspection Commercial Flat Roof
2026-08-07 - 2026-RESCON-0002241
10:30 AM - 12:30 PM: 113 - Pre Construction Meeting
2026-07-29 - 2026-RESCON-0002241
08:30 AM - 10:30 AM: 113 - Pre Construction Meeting
2620 Walnut ST
Recent Inspections
2026-09-11 - 2026-ELEC-0003905
08:30 AM - 10:30 AM: 304 - Partial Final
2026-09-10 - 2026-PLUMB-0006188
08:00 AM - 10:00 AM: 403 - Pressure Test
2026-09-08 - 2026-COMMCON-0000506
09:00 AM - 11:00 AM: 107 - Drywall
09:00 AM - 11:00 AM: 109 - Other
09:00 AM - 11:00 AM: 112 - Frame
2026-09-04 - 2026-FIRE-0003920
08:00 AM - 10:00 AM: 411 - Rough
2026-09-04 - 2026-COMMCON-0000506
11:00 AM - 01:00 PM: 107 - Drywall
2026-09-04 - 2026-ELEC-0003905
08:30 AM - 09:30 AM: 302 - Partial Rough
2026-09-03 - 2026-FIRE-0003879
08:30 AM - 05:30 PM: 302 - Partial Rough
2026-09-03 - 2026-ELEC-0003905
08:30 AM - 09:30 AM: 302 - Partial Rough
2026-09-01 - 2026-FIRE-0003879
08:00 AM - 10:30 AM: 302 - Partial Rough
2026-09-01 - 2026-ELEC-0003905
08:00 AM - 10:30 AM: 302 - Partial Rough
2026-08-31 - 2026-FIRE-0003879
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-08-31 - 2026-FIRE-0003920
08:00 AM - 10:00 AM: 411 - Rough
2026-08-31 - 2026-ELEC-0003905
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-08-19 - 2026-COMMCON-0000506
09:00 AM - 11:00 AM: 107 - Drywall
2026-08-19 - 2026-ELEC-0003905
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-08-17 - 2026-ELEC-0003905
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-08-14 - 2026-COMMCON-0000506
01:00 PM - 03:00 PM: 106 - Batt Insulation
2026-08-11 - 2026-COMMCON-0000506
09:00 AM - 11:00 AM: 112 - Frame
2026-08-11 - 2026-ELEC-0003905
10:00 AM - 12:30 PM: 304 - Partial Final
TBD: 302 - Partial Rough
2026-08-10 - 2026-ELEC-0003905
10:00 AM - 12:30 PM: 302 - Partial Rough
2026-08-07 - 2026-PLUMB-0006188
10:00 AM - 12:00 PM: 401 - Rough
10:00 AM - 12:00 PM: 403 - Pressure Test
2026-08-06 - 2026-MECH-0001671
11:00 AM - 01:00 PM: 903 - Rough
2026-08-04 - 2026-PLUMB-0006188
11:00 AM - 02:00 PM: 400 - Groundwork
2026-07-31 - 2026-ELEC-0003905
08:30 AM - 10:30 AM: 302 - Partial Rough
2026-07-30 - 2026-ELEC-0003905
10:00 AM - 12:00 PM: 301 - Underground
2026-07-28 - 2026-COMMCON-0000506
09:00 AM - 11:00 AM: 500 - Rough
TBD: 112 - Frame