2373 N Central Park BLVD
Recent Inspections
2026-10-27 - 2026-PLUMB-0007445
08:30 AM - 10:30 AM: 400 - Groundwork
08:30 AM - 10:30 AM: 401 - Rough
2026-07-09 - 2026-ELEC-0004089
12:00 PM - 02:30 PM: 305 - Final - Electrical
2026-07-02 - 2026-ELEC-0004089
08:30 AM - 10:30 AM: 305 - Final - Electrical
2026-07-01 - 2026-ELEC-0004089
11:00 AM - 01:00 PM: 305 - Final - Electrical
2026-06-25 - 2026-ROOFSIDE-0001712
09:30 AM - 11:30 AM: 201 - Final - Roof
2026-06-22 - 2026-ROOFSIDE-0001712
11:00 AM - 01:00 PM: 201 - Final - Roof
3975 N Shoshone ST
Recent Inspections
2026-10-27 - 2026-PLUMB-0005015
08:00 AM - 10:30 AM: 402 - Final - Plumbing
2026-10-07 - 2026-DEMO-0000426
08:30 AM - 05:30 PM: Demolition Final Inspection
2026-10-02 - 2026-ELEC-0005418
08:30 AM - 10:30 AM: 305 - Final - Electrical
2026-09-04 - 2026-DEMO-0000426
10:30 AM - 12:30 PM: Safe Site Inspection
2026-06-30 - 2026-RESCON-0001511
10:30 AM - 12:30 PM: 107 - Drywall
2026-06-30 - 2026-ROOFSIDE-0002188
10:30 AM - 12:30 PM: 201 - Final - Roof
2026-06-25 - 2026-RESCON-0001511
09:00 AM - 11:00 AM: 107 - Drywall
2026-06-23 - 2026-RESCON-0001511
10:30 AM - 12:30 PM: 112 - Frame
2026-06-22 - 2026-RESCON-0001511
08:30 AM - 05:30 PM: 112 - Frame
2915 N Raleigh ST
Recent Inspections
2026-10-27 - 2026-RESCON-0001251
09:00 AM - 11:00 AM: 108 - Final - Residential
2026-10-27 - 2026-ELEC-0007913
01:00 PM - 03:00 PM: 305 - Final - Electrical
2026-10-27 - 2026-PLUMB-0005565
11:00 AM - 01:00 PM: 402 - Final - Plumbing
2026-09-11 - 2026-RESCON-0001251
11:00 AM - 01:00 PM: 107 - Drywall
2026-09-04 - 2026-RESCON-0001251
09:00 AM - 11:00 AM: 106 - Batt Insulation
2026-09-02 - 2026-RESCON-0001251
09:00 AM - 11:00 AM: 112 - Frame
2026-09-01 - 2026-MECH-0005491
10:00 AM - 12:00 PM: 903 - Rough
2026-09-01 - 2026-PLUMB-0005565
09:00 AM - 11:00 AM: 401 - Rough
2026-08-28 - 2026-ELEC-0007913
11:00 AM - 01:00 PM: 303 - Full Rough
11:00 AM - 01:00 PM: 307 - Service Equipment
11:00 AM - 01:00 PM: 313 - Meter Release
2026-08-26 - 2026-RESCON-0001251
11:00 AM - 01:00 PM: Document Review
2026-08-03 - 2026-RESCON-0001251
09:00 AM - 11:00 AM: 116 - Building Slab
2026-07-30 - 2026-RESCON-0001251
11:00 AM - 01:00 PM: 102 - Foundation Perimeter Drain
2026-07-13 - 2026-PLUMB-0005565
11:00 AM - 02:00 PM: 400 - Groundwork
934 S Washington ST
Recent Inspections
2026-10-27 - 2026-ELEC-0005604
09:00 AM - 11:00 AM: 305 - Final - Electrical
09:00 AM - 11:00 AM: 307 - Service Equipment
09:00 AM - 11:00 AM: 313 - Meter Release
2026-10-27 - 2026-PLUMB-0004845
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-08-07 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 107 - Drywall
2026-08-06 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 107 - Drywall
2026-07-30 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 106 - Batt Insulation
09:00 AM - 11:00 AM: 112 - Frame
2026-07-28 - 2026-ROOFSIDE-0002923
09:00 AM - 11:00 AM: 201 - Final - Roof
2026-07-15 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 106 - Batt Insulation
01:00 PM - 03:00 PM: 112 - Frame
2026-07-10 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 112 - Frame
2026-07-08 - 2026-RESCON-0001176
01:00 PM - 03:00 PM: 112 - Frame
2026-07-06 - 2026-MECH-0004042
11:00 AM - 01:00 PM: 904 - Final - Mechanical
2026-07-02 - 2026-ELEC-0005604
08:30 AM - 09:30 AM: 305 - Final - Electrical
2026-07-01 - 2026-ELEC-0005604
01:00 PM - 03:00 PM: 305 - Final - Electrical
TBD: 307 - Service Equipment
TBD: 313 - Meter Release
2026-06-29 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 113 - Pre Construction Meeting
2026-06-26 - 2026-PLUMB-0004845
01:00 PM - 03:00 PM: 401 - Rough
01:00 PM - 03:00 PM: 403 - Pressure Test
2026-06-26 - 2026-RESCON-0001176
09:00 AM - 11:00 AM: 113 - Pre Construction Meeting
2026-06-25 - 2026-PLUMB-0004845
01:00 PM - 03:00 PM: 401 - Rough
01:00 PM - 03:00 PM: 403 - Pressure Test
2026-06-23 - 2026-RESCON-0001176
08:30 AM - 05:30 PM: 113 - Pre Construction Meeting
1149 S Race ST
Recent Inspections
2026-10-27 - 2026-ELEC-0007190
09:00 AM - 11:00 AM: 305 - Final - Electrical
2026-10-26 - 2026-MECH-0003507
09:00 AM - 11:00 AM: 904 - Final - Mechanical
2026-10-23 - 2026-MECH-0005091
01:00 PM - 03:00 PM: 904 - Final - Mechanical
2026-10-23 - 2026-PLUMB-0006674
08:30 AM - 11:30 AM: 402 - Final - Plumbing
2026-10-21 - 2026-PLUMB-0006674
10:30 AM - 12:30 PM: 402 - Final - Plumbing
2026-10-20 - 2026-PLUMB-0006674
08:00 AM - 10:00 AM: 402 - Final - Plumbing
2026-09-03 - 2026-RESCON-0001457
08:30 AM - 10:30 AM: 107 - Drywall
2026-09-03 - 2026-ELEC-0007190
11:00 AM - 01:00 PM: 302 - Partial Rough
2026-08-28 - 2026-RESCON-0001457
11:00 AM - 01:00 PM: 107 - Drywall
2026-08-27 - 2026-RESCON-0001457
09:00 AM - 11:00 AM: 106 - Batt Insulation
09:00 AM - 11:00 AM: 107 - Drywall
2026-08-26 - 2026-RESCON-0001457
12:00 PM - 02:00 PM: 112 - Frame
2026-08-26 - 2026-ELEC-0007190
10:00 AM - 12:00 PM: 303 - Full Rough
2026-08-21 - 2026-ELEC-0007190
09:00 AM - 11:00 AM: 302 - Partial Rough
2026-08-13 - 2026-PLUMB-0006674
08:30 AM - 09:30 AM: 401 - Rough
2026-08-12 - 2026-MECH-0005091
09:00 AM - 11:00 AM: 903 - Rough
2026-07-22 - 2026-RESCON-0001457
01:00 PM - 03:00 PM: 113 - Pre Construction Meeting
2026-07-21 - 2026-RESCON-0001457
01:00 PM - 03:00 PM: 113 - Pre Construction Meeting