205 N Detroit St

Directions

Recent Inspections

2026-10-27 - 2026-ELEC-0010044

08:00 AM - 10:00 AM: 305 - Final - Electrical

2026-10-23 - 2026-COMMCON-0002011

11:00 AM - 01:00 PM: 112 - Frame

2026-10-23 - 2026-ELEC-0010044

09:00 AM - 11:00 AM: 303 - Full Rough

2026-10-21 - 2026-COMMCON-0002011

01:00 PM - 03:00 PM: 113 - Pre Construction Meeting

1678 N Vrain ST

Directions

Recent Inspections

2026-10-26 - 2026-RESCON-0002194

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

910 N Mariposa ST

Directions

Recent Inspections

2026-10-26 - 2025-RESCON-0000893

09:30 AM - 11:00 AM: 109 - Other

2026-10-26 - 2025-RESCON-0000894

09:30 AM - 11:00 AM: 109 - Other

2026-10-19 - 2026-ELEC-0000387

09:00 AM - 11:00 AM: 305 - Final - Electrical

2026-10-16 - 2026-MECH-0000806

TBD: Document Review

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-16 - 2026-MECH-0000808

TBD: Document Review

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-08 - 2025-RESCON-0000893

09:00 AM - 11:00 AM: 108 - Final - Residential

09:00 AM - 11:00 AM: 200 - Blown Insulation

2026-10-08 - 2025-RESCON-0000894

09:00 AM - 11:00 AM: 108 - Final - Residential

09:00 AM - 11:00 AM: 200 - Blown Insulation

2026-10-08 - 2026-ROOFSIDE-0001370

09:00 AM - 11:00 AM: 201 - Final - Roof

2026-10-08 - 2026-ROOFSIDE-0001371

09:00 AM - 11:00 AM: 201 - Final - Roof

2026-10-08 - 2026-ROOFSIDE-0001372

09:00 AM - 11:00 AM: 201 - Final - Roof

2026-10-08 - 2026-ROOFSIDE-0001373

09:00 AM - 11:00 AM: 201 - Final - Roof

2026-10-08 - 2026-ELEC-0000391

12:00 PM - 02:00 PM: 305 - Final - Electrical

2026-10-07 - 2026-MECH-0000806

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-07 - 2026-MECH-0000808

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-06 - 2026-MECH-0000806

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-06 - 2026-MECH-0000808

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-10-05 - 2026-ELEC-0000389

12:00 PM - 02:00 PM: 305 - Final - Electrical

2026-10-05 - 2026-ELEC-0000391

12:00 PM - 02:00 PM: 305 - Final - Electrical

2026-10-05 - 2026-ELEC-0000393

12:00 PM - 02:00 PM: 305 - Final - Electrical

2026-09-15 - 2026-ELEC-0000389

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-09-15 - 2026-ELEC-0000391

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-09-15 - 2026-ELEC-0000393

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-09-15 - 2026-ELEC-0000387

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-09-11 - 2026-ELEC-0000387

08:30 AM - 09:30 AM: 305 - Final - Electrical

2026-09-11 - 2026-ELEC-0000391

08:30 AM - 09:30 AM: 305 - Final - Electrical

2026-08-26 - 2025-PLUMB-0009284

08:00 AM - 10:30 AM: 402 - Final - Plumbing

2026-08-26 - 2025-PLUMB-0009286

08:00 AM - 11:00 AM: 402 - Final - Plumbing

2026-07-13 - 2026-ELEC-0000389

12:00 PM - 02:00 PM: 303 - Full Rough

2026-07-13 - 2026-ELEC-0000393

12:00 PM - 02:00 PM: 303 - Full Rough

2026-07-10 - 2026-ELEC-0000389

10:00 AM - 12:00 PM: 303 - Full Rough

2026-07-10 - 2026-ELEC-0000393

10:00 AM - 12:00 PM: 303 - Full Rough

8700 Pena BLVD

Directions

Recent Inspections

2026-10-27 - 2024-ELEC-0004084

12:30 PM - 02:30 PM: 304 - Partial Final

2026-10-27 - 2026-PLUMB-0005371

01:00 PM - 03:00 PM: 401 - Rough

2026-10-27 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 703 - Rough

2026-10-23 - 2026-COMMCON-0000203

11:00 AM - 01:00 PM: Document Review Inspection

11:00 AM - 01:00 PM: 108 - Final - Commercial

11:00 AM - 01:00 PM: 109 - Other

2026-10-23 - 2026-COMMCON-0000496

11:00 AM - 01:00 PM: 107 - Drywall

2026-10-23 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-22 - 2026-FIRE-0002297

01:00 PM - 03:00 PM: 411 - Rough

2026-10-22 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-10-22 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-22 - 2026-PLUMB-0001151

01:00 PM - 03:00 PM: 402 - Final - Plumbing

2026-10-21 - 2026-COMMCON-0000496

08:30 AM - 09:30 AM: 107 - Drywall

2026-10-21 - 2026-FIRE-0002866

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-10-21 - 2026-FIRE-0004275

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-10-21 - 2025-ELEC-0012390

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-21 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 305 - Final - Electrical

10:00 AM - 12:00 PM: 308 - Ceiling

2026-10-21 - 2026-PLUMB-0001151

09:00 AM - 11:00 AM: 402 - Final - Plumbing

2026-10-20 - 2026-FIRE-0005403

12:30 PM - 02:30 PM: 303 - Full Rough

2026-10-20 - 2026-COMMCON-0000496

08:30 AM - 09:30 AM: 107 - Drywall

08:30 AM - 09:30 AM: 112 - Frame

2026-10-19 - 2026-MECH-0003702

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-10-16 - 2026-FIRE-0004275

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-10-16 - 2026-COMMCON-0000496

01:00 AM - 03:00 PM: 112 - Frame

01:00 AM - 03:00 PM: 113 - Pre Construction Meeting

2026-10-15 - 2025-COMMCON-0001187

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-10-14 - 2026-FIRE-0002684

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-10-14 - 2026-FIRE-0004669

10:00 AM - 12:00 PM: 303 - Full Rough

2026-10-14 - 2026-FIRE-0005472

10:00 AM - 12:00 PM: 303 - Full Rough

2026-10-14 - 2025-ELEC-0011640

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-10-14 - 2026-COMMCON-0000496

08:30 AM - 09:30 AM: 112 - Frame

2026-10-13 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: Document Review Inspection

2026-10-13 - 2026-COMMCON-0000496

01:00 PM - 03:00 PM: 112 - Frame

2026-10-09 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 109 - Other

2026-10-09 - 2026-ELEC-0001470

12:30 PM - 02:30 PM: 304 - Partial Final

2026-10-08 - 2026-COMMCON-0000203

TBD: Document Review Inspection

2026-10-08 - 2026-ACCCON-0000256

01:00 PM - 03:00 PM: 304 - Partial Final

2026-10-08 - 2026-FIRE-0005306

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-10-08 - 2026-FIRE-0005477

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-10-08 - 2026-ELEC-0004635

12:30 PM - 02:30 PM: 308 - Ceiling

2026-10-07 - 2025-FIRE-0004767

10:00 AM - 12:00 PM: 303 - Full Rough

2026-10-07 - 2025-FIRE-0005355

10:00 AM - 12:00 PM: 303 - Full Rough

2026-10-07 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 308 - Ceiling

2026-10-07 - 2026-ELEC-0007375

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-06 - 2024-ELEC-0004084

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-10-06 - 2026-MECH-0000831

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-10-06 - 2026-PLUMB-0005957

09:00 AM - 11:00 AM: 401 - Rough

2026-10-05 - 2026-FIRE-0002297

11:00 AM - 01:00 PM: 411 - Rough

2026-10-05 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 308 - Ceiling

2026-10-02 - 2026-EC-0000086

TBD: Waiting to Start

2026-10-02 - 2026-ACCCON-0000256

11:30 AM - 01:00 PM: 304 - Partial Final

2026-10-02 - 2026-PLUMB-0005371

01:00 PM - 03:00 PM: 401 - Rough

2026-10-01 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: Document Review Inspection

11:00 AM - 01:00 PM: 109 - Other

2026-10-01 - 2025-FIRE-0005353

12:30 PM - 02:30 PM: 306 - Final - Conduit Only

TBD: 303 - Full Rough

2026-10-01 - 2026-COMMCON-0000807

01:00 PM - 03:00 PM: 112 - Frame

2026-10-01 - 2026-EC-0000086

TBD: Waiting to Start

2026-09-30 - 2025-DEMO-0000082

08:30 AM - 05:30 PM: Demolition Final Inspection

2026-09-30 - 2025-COMMCON-0000752

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0000784

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0001012

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0001029

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0001165

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0001191

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0002013

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2025-COMMCON-0002766

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-09-30 - 2026-MECH-0000446

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-29 - 2026-ELEC-0001470

12:30 PM - 02:30 PM: 304 - Partial Final

2026-09-29 - 2026-ELEC-0004635

12:30 PM - 02:30 PM: 309 - Walls

2026-09-28 - 2026-PLUMB-0005371

01:00 PM - 03:00 PM: 401 - Rough

2026-09-25 - 2026-FIRE-0002866

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-25 - 2026-FIRE-0004275

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-25 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 109 - Other

2026-09-25 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 304 - Partial Final

10:00 AM - 12:00 PM: 308 - Ceiling

2026-09-24 - 2025-FIRE-0004737

12:30 PM - 02:30 PM: 306 - Final - Conduit Only

2026-09-24 - 2026-ELEC-0001470

12:30 PM - 02:30 PM: 308 - Ceiling

2026-09-24 - 2026-MECH-0003702

09:00 AM - 11:00 AM: 903 - Rough

2026-09-23 - 2025-FIRE-0002434

12:00 PM - 02:00 PM: 303 - Full Rough

2026-09-23 - 2026-COMMCON-0000807

01:00 PM - 03:00 PM: 112 - Frame

2026-09-22 - 2026-COMMCON-0000203

08:30 AM - 09:30 AM: 109 - Other

2026-09-21 - 2025-COMMCON-0002096

01:00 PM - 03:00 PM: Document Review Inspection

2026-09-21 - 2024-COMMCON-0002420

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-09-18 - 2025-MECH-0000763

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-17 - 2026-FIRE-0002297

09:00 AM - 11:00 AM: 411 - Rough

2026-09-17 - 2025-COMMCON-0002096

01:00 PM - 03:00 PM: 108 - Final - Commercial

01:00 PM - 03:00 PM: 109 - Other

2026-09-17 - 2025-COMMCON-0002686

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-09-17 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 108 - Final - Commercial

01:00 PM - 03:00 PM: 109 - Other

2026-09-16 - 2025-BOILERAC-0000746

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-09-16 - 2025-MECH-0006474

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-16 - 2026-PLUMB-0001151

11:00 AM - 02:00 PM: 402 - Final - Plumbing

2026-09-16 - 2026-PLUMB-0005090

11:00 AM - 02:00 PM: 403 - Pressure Test

2026-09-14 - 2025-PLUMB-0008698

11:00 AM - 02:00 PM: 402 - Final - Plumbing

2026-09-14 - 2026-MECH-0004033

09:00 AM - 11:00 AM: 903 - Rough

2026-09-14 - 2026-PLUMB-0001151

11:00 AM - 02:00 PM: 402 - Final - Plumbing

2026-09-14 - 2026-PLUMB-0005090

11:00 AM - 02:00 PM: 403 - Pressure Test

2026-09-11 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-09-11 - 2026-FIRE-0003226

12:30 PM - 02:30 PM: 303 - Full Rough

2026-09-11 - 2026-FIRE-0003754

12:30 PM - 02:30 PM: 303 - Full Rough

2026-09-11 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 109 - Other

2026-09-11 - 2026-ELEC-0001470

12:30 PM - 02:30 PM: 304 - Partial Final

2026-09-11 - 2026-PLUMB-0001151

10:00 AM - 12:00 PM: 402 - Final - Plumbing

2026-09-10 - 2025-FIRE-0007538

10:00 AM - 12:00 PM: 303 - Full Rough

2026-09-10 - 2026-FIRE-0002866

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-10 - 2026-FIRE-0003776

01:00 PM - 03:00 PM: 412 - Final - Fire Suppression

2026-09-10 - 2026-FIRE-0004275

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-10 - 2024-COMMCON-0002420

01:00 PM - 03:00 PM: 109 - Other

2026-09-10 - 2025-ELEC-0001076

10:00 AM - 12:00 PM: 304 - Partial Final

2026-09-10 - 2026-ELEC-0000050

12:30 PM - 02:30 PM: 305 - Final - Electrical

2026-09-10 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 308 - Ceiling

2026-09-10 - 2026-MECH-0000831

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-09 - 2025-ELEC-0001197

10:00 AM - 12:00 PM: 304 - Partial Final

TBD: 305 - Final - Electrical

2026-09-09 - 2025-ELEC-0005809

12:30 PM - 02:30 PM: 305 - Final - Electrical

2026-09-09 - 2025-ELEC-0011640

10:00 AM - 12:00 PM: 304 - Partial Final

2026-09-09 - 2026-ELEC-0005133

10:00 AM - 12:00 PM: 304 - Partial Final

2026-09-09 - 2026-ELEC-0006664

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-08 - 2026-COMMCON-0000203

TBD: Document Review Inspection

2026-09-08 - 2026-FIRE-0000912

10:00 AM - 12:00 PM: 412 - Final - Fire Suppression

2026-09-08 - 2026-ELEC-0008221

10:00 AM - 12:00 PM: 304 - Partial Final

2026-09-08 - 2026-PLUMB-0005957

10:00 AM - 12:00 PM: 403 - Pressure Test

2026-09-08 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 702 - Partial Rough

2026-09-04 - 2026-COMMCON-0000203

10:30 AM - 12:30 PM: 108 - Final - Commercial

10:30 AM - 12:30 PM: 109 - Other

2026-09-03 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-09-03 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-02 - 2025-BOILERAC-0000076

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-09-02 - 2025-DEMO-0000084

01:00 AM - 03:00 PM: Demolition Final Inspection

2026-09-02 - 2025-MECH-0002463

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-02 - 2025-MECH-0003223

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-09-02 - 2025-MECH-0003815

11:00 AM - 01:00 PM: 904 - Final - Mechanical

2026-09-02 - 2025-MECH-0004450

11:00 AM - 01:00 PM: 904 - Final - Mechanical

2026-09-02 - 2026-MECH-0000428

11:00 AM - 01:00 PM: 902 - Partial Rough

2026-09-02 - 2026-PLUMB-0001151

01:00 PM - 03:00 PM: 401 - Rough

2026-09-01 - 2026-FIRE-0003513

10:00 AM - 12:00 PM: 303 - Full Rough

2026-09-01 - 2024-COMMCON-0002420

11:00 AM - 01:00 PM: 108 - Final - Commercial

2026-09-01 - 2025-COMMCON-0002096

11:00 AM - 01:00 PM: 109 - Other

2026-09-01 - 2025-ELEC-0011784

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-09-01 - 2026-ELEC-0006664

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-31 - 2025-FIRE-0003968

10:00 AM - 12:00 PM: 303 - Full Rough

2026-08-31 - 2026-FIRE-0002684

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-31 - 2026-FIRE-0004669

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-31 - 2025-COMMCON-0000210

01:30 PM - 03:00 PM: 108 - Final - Commercial

2026-08-31 - 2025-ELEC-0003084

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-08-31 - 2025-ELEC-0011640

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-31 - 2026-COMMCON-0000203

01:30 PM - 03:00 PM: 109 - Other

2026-08-28 - 2025-PLUMB-0004868

11:00 AM - 01:00 PM: 402 - Final - Plumbing

2026-08-28 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-28 - 2026-PLUMB-0004742

01:00 PM - 03:00 PM: 401 - Rough

2026-08-27 - 2025-COMMCON-0000210

11:00 AM - 01:00 PM: Document Review Inspection

11:00 AM - 01:00 PM: 109 - Other

2026-08-27 - 2026-FIRE-0003776

01:00 PM - 03:00 PM: 411 - Rough

2026-08-26 - 2025-FIRE-0001198

12:30 PM - 02:30 PM: 306 - Final - Conduit Only

12:30 PM - 02:30 PM: 303 - Full Rough

2026-08-26 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-08-26 - 2026-MECH-0000831

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-08-21 - 2026-FIRE-0002866

10:00 AM - 12:00 PM: 303 - Full Rough

2026-08-21 - 2026-FIRE-0004275

10:00 AM - 12:00 PM: 303 - Full Rough

2026-08-21 - 2026-COMMCON-0000203

08:30 AM - 09:30 AM: 109 - Other

2026-08-21 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 304 - Partial Final

2026-08-20 - 2024-FIRE-0007246

11:00 AM - 01:00 PM: 412 - Final - Fire Suppression

2026-08-20 - 2024-FIRE-0007284

11:00 AM - 01:00 PM: 412 - Final - Fire Suppression

2026-08-20 - 2025-FIRE-0002964

11:00 AM - 01:00 PM: 412 - Final - Fire Suppression

2026-08-20 - 2025-MECH-0006474

09:00 AM - 11:00 AM: 901 - Pressure Test

2026-08-19 - 2025-COMMCON-0001187

12:00 PM - 01:00 PM: 107 - Drywall

2026-08-19 - 2026-COMMCON-0000203

12:00 PM - 01:00 PM: 109 - Other

2026-08-19 - 2026-ELEC-0007464

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-08-17 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 308 - Ceiling

2026-08-13 - 2025-PLUMB-0001081

08:30 AM - 09:30 AM: 402 - Final - Plumbing

2026-08-11 - 2024-ELEC-0013471

12:30 PM - 02:30 PM: 305 - Final - Electrical

2026-08-07 - 2025-MECH-0006474

09:00 AM - 11:00 AM: 903 - Rough

2026-08-06 - 2025-FIRE-0001217

11:00 AM - 01:00 PM: 411 - Rough

2026-08-06 - 2026-FIRE-0002684

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-08-06 - 2025-ELEC-0011640

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-08-05 - 2025-PLUMB-0008698

11:00 AM - 01:00 PM: 401 - Rough

2026-08-04 - 2026-FIRE-0000912

09:00 AM - 11:00 AM: 411 - Rough

2026-08-04 - 2025-COMMCON-0002686

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-03 - 2026-ELEC-0000050

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-31 - 2025-COMMCON-0002686

08:30 AM - 10:30 AM: 112 - Frame

2026-07-31 - 2025-MECH-0000763

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-07-31 - 2026-COMMCON-0001124

08:30 AM - 10:30 AM: 109 - Other

2026-07-31 - 2026-ELEC-0005500

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-30 - 2025-ELEC-0011640

08:30 AM - 09:30 AM: 302 - Partial Rough

2026-07-30 - 2025-PLUMB-0008698

12:00 PM - 02:00 PM: 401 - Rough

2026-07-30 - 2026-COMMCON-0001124

08:30 AM - 09:30 AM: 109 - Other

2026-07-30 - 2026-ELEC-0000050

08:30 AM - 09:30 AM: 302 - Partial Rough

2026-07-30 - 2026-ELEC-0005500

08:30 AM - 09:30 AM: 302 - Partial Rough

2026-07-30 - 2026-MECH-0003369

09:00 AM - 11:00 AM: 901 - Pressure Test

2026-07-29 - 2026-FIRE-0003831

10:00 AM - 12:00 PM: 303 - Full Rough

2026-07-29 - 2026-COMMCON-0000094

01:00 PM - 03:00 PM: 109 - Other

2026-07-28 - 2025-PLUMB-0011393

11:00 AM - 02:00 PM: 402 - Final - Plumbing

2026-07-28 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 109 - Other

2026-07-27 - 2025-COMMCON-0000210

01:00 PM - 03:00 PM: 109 - Other

2026-07-24 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 109 - Other

2026-07-24 - 2026-BOILERAC-0000108

11:00 AM - 01:00 PM: 702 - Partial Rough

2026-07-22 - 2026-FIRE-0003654

10:00 AM - 12:00 PM: 303 - Full Rough

2026-07-22 - 2026-MECH-0003369

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-07-22 - 2026-PLUMB-0001151

11:00 AM - 01:00 PM: 401 - Rough

2026-07-21 - 2026-COMMCON-0000203

09:30 AM - 12:00 PM: 107 - Drywall

2026-07-20 - 2026-PLUMB-0000645

09:00 AM - 11:00 AM: 401 - Rough

2026-07-20 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 702 - Partial Rough

2026-07-17 - 2025-FIRE-0007538

12:30 PM - 02:30 PM: 303 - Full Rough

2026-07-17 - 2024-COMMCON-0002420

08:30 AM - 11:00 AM: 109 - Other

2026-07-17 - 2025-ELEC-0001076

12:30 PM - 02:30 PM: 304 - Partial Final

2026-07-17 - 2026-COMMCON-0000203

08:30 AM - 11:00 AM: 109 - Other

2026-07-16 - 2026-FIRE-0002866

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-16 - 2025-ELEC-0001197

12:30 PM - 02:30 PM: 308 - Ceiling

2026-07-16 - 2026-ELEC-0001470

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-15 - 2026-MECH-0000831

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-07-13 - 2026-COMMCON-0000203

10:00 AM - 12:30 PM: 107 - Drywall

2026-07-13 - 2026-COMMCON-0000496

10:00 AM - 12:30 PM: 112 - Frame

10:00 AM - 12:30 PM: 113 - Pre Construction Meeting

2026-07-10 - 2026-COMMCON-0001043

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-07-09 - 2026-COMMCON-0001043

01:00 AM - 03:00 PM: 108 - Final - Commercial

2026-07-09 - 2026-BOILERAC-0000108

09:00 AM - 11:00 AM: 703 - Rough

2026-07-08 - 2025-COMMCON-0001709

01:00 PM - 03:00 PM: 108 - Final - Commercial

2026-07-08 - 2026-COMMCON-0000203

01:00 PM - 03:00 PM: 107 - Drywall

2026-07-08 - 2026-ELEC-0004807

08:00 AM - 10:00 AM: 305 - Final - Electrical

2026-07-07 - 2026-ELEC-0004807

08:30 AM - 09:30 AM: 305 - Final - Electrical

08:30 AM - 09:30 AM: 311 - Temporary Service

2026-07-06 - 2025-COMMCON-0001709

11:00 AM - 02:00 PM: 108 - Final - Commercial

2026-07-06 - 2026-COMMCON-0000203

11:00 AM - 02:00 PM: 107 - Drywall

2026-07-02 - 2025-FIRE-0002964

10:00 AM - 12:00 PM: 411 - Rough

2026-07-02 - 2024-COMMCON-0002420

09:00 AM - 11:00 AM: 109 - Other

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2026-07-02 - 2025-COMMCON-0002096

09:00 AM - 11:00 AM: 112 - Frame

2026-07-02 - 2025-ELEC-0012390

10:00 AM - 12:00 PM: 304 - Partial Final

2026-07-02 - 2025-PLUMB-0008698

10:00 AM - 12:00 PM: 401 - Rough

2026-07-02 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-07-02 - 2025-COMMCON-0001987

TBD: 108 - Final - Commercial

2026-07-01 - 2025-COMMCON-0001709

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-06-30 - 2026-COMMCON-0001124

08:30 AM - 09:30 AM: 113 - Pre Construction Meeting

2026-06-30 - 2025-COMMCON-0001987

08:00 AM - 10:00 AM: 108 - Final - Commercial

2026-06-30 - 2025-MECH-0005291

08:30 AM - 09:30 AM: 904 - Final - Mechanical

2026-06-30 - 2026-COMMCON-0000203

08:00 AM - 10:00 AM: 107 - Drywall

2026-06-30 - 2026-ELEC-0003923

08:00 AM - 10:00 AM: 305 - Final - Electrical

2026-06-29 - 2022-COMMCON-0001576

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-06-29 - 2026-COMMCON-0001124

08:30 AM - 09:30 AM: 113 - Pre Construction Meeting

2026-06-29 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-06-26 - 2025-MECH-0005291

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-06-26 - 2026-COMMCON-0001124

01:00 PM - 03:00 PM: 113 - Pre Construction Meeting

2026-06-25 - 2025-COMMCON-0001709

10:30 AM - 12:30 PM: 108 - Final - Commercial

2026-06-25 - 2025-COMMCON-0001987

10:30 AM - 12:30 PM: 108 - Final - Commercial

2026-06-23 - 2025-FIRE-0001217

01:00 PM - 03:00 PM: 411 - Rough

2026-06-23 - 2026-FIRE-0000686

08:00 AM - 10:00 AM: 303 - Full Rough

2026-06-23 - 2026-FIRE-0000976

08:00 AM - 10:00 AM: 303 - Full Rough

2026-06-23 - 2026-FIRE-0001972

08:00 AM - 10:00 AM: 303 - Full Rough

2026-06-23 - 2026-FIRE-0002245

08:00 AM - 10:00 AM: 303 - Full Rough

2026-06-23 - 2026-FIRE-0002684

08:00 AM - 10:00 AM: 302 - Partial Rough

2026-06-23 - 2025-ELEC-0008570

08:00 AM - 10:00 AM: 305 - Final - Electrical

08:00 AM - 10:00 AM: 308 - Ceiling

2026-06-23 - 2025-ELEC-0011640

08:00 AM - 10:00 AM: 302 - Partial Rough

2026-06-23 - 2025-PLUMB-0007243

01:00 PM - 03:00 PM: 402 - Final - Plumbing

2026-06-22 - 2026-FIRE-0001972

10:00 AM - 12:00 PM: 303 - Full Rough

2026-06-22 - 2026-FIRE-0002684

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-06-22 - 2024-MECH-0002178

09:00 AM - 11:00 AM: 902 - Partial Rough

2026-06-22 - 2025-ELEC-0011640

10:00 AM - 12:00 PM: 302 - Partial Rough

2026-06-22 - 2026-ELEC-0001470

10:00 AM - 12:00 PM: 302 - Partial Rough

511 16th ST

Directions

Recent Inspections

2026-10-27 - 2026-FIRE-0004920

08:00 AM - 10:00 AM: 411 - Rough

2026-10-22 - 2026-COMMCON-0000335

09:00 AM - 11:00 AM: 112 - Frame

2026-10-21 - 2025-ELEC-0005547

08:00 AM - 10:00 AM: 305 - Final - Electrical

2026-10-21 - 2026-ELEC-0001814

08:00 AM - 10:00 AM: 308 - Ceiling

2026-10-20 - 2026-ELEC-0001814

08:00 AM - 10:00 AM: 308 - Ceiling

2026-10-13 - 2026-PLUMB-0002002

12:30 PM - 03:00 PM: 401 - Rough

2026-10-08 - 2026-ELEC-0001814

08:00 AM - 11:00 AM: 309 - Walls

2026-10-08 - 2026-PLUMB-0002002

10:30 AM - 12:30 PM: 401 - Rough

2026-08-21 - 2025-FIRE-0003095

08:00 AM - 10:00 AM: 303 - Full Rough

2026-08-18 - 2025-ELEC-0005547

08:00 AM - 10:00 AM: 304 - Partial Final

2026-08-13 - 2025-COMMCON-0002138

08:30 AM - 09:30 AM: 108 - Final - Commercial

08:30 AM - 09:30 AM: 121 - Certificate of Occupancy

2026-08-10 - 2025-COMMCON-0002138

09:00 AM - 11:00 AM: 108 - Final - Commercial

09:00 AM - 11:00 AM: 121 - Certificate of Occupancy

2026-08-10 - 2026-COMMCON-0000262

09:00 AM - 11:00 AM: 108 - Final - Commercial

09:00 AM - 11:00 AM: 121 - Certificate of Occupancy

2026-08-05 - 2026-MECH-0001031

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-08-03 - 2025-MECH-0006599

09:00 AM - 11:00 AM: 904 - Final - Mechanical

2026-07-31 - 2025-MECH-0006599

09:00 AM - 11:00 AM: 904 - Final - Mechanical

09:00 AM - 11:00 AM: Document Review

2026-06-29 - 2025-MECH-0006599

09:00 AM - 11:00 AM: Document Review

4600 S Syracuse ST

Directions

Recent Inspections

2026-10-27 - 2026-COMMCON-0002014

11:00 AM - 01:00 PM: 113 - Pre Construction Meeting

2026-10-26 - 2026-COMMCON-0002014

12:00 PM - 02:00 PM: 113 - Pre Construction Meeting

2026-08-18 - 2026-COMMCON-0000492

12:00 PM - 02:00 PM: 108 - Final - Commercial

2026-08-17 - 2026-ACCCON-0000193

TBD: 305 - Final - Access Control

2026-08-17 - 2026-MECH-0002606

TBD: Document Review

01:00 PM - 03:00 PM: 904 - Final - Mechanical

2026-08-17 - 2026-COMMCON-0000492

08:30 AM - 09:30 AM: 108 - Final - Commercial

2026-08-14 - 2026-FIRE-0001583

08:30 AM - 11:30 AM: 412 - Final - Fire Suppression

2026-08-13 - 2026-ELEC-0002861

12:00 PM - 02:00 PM: 305 - Final - Electrical

08:30 AM - 09:30 AM: 307 - Service Equipment

2026-08-13 - 2026-PLUMB-0003750

08:30 AM - 09:30 AM: 402 - Final - Plumbing

2026-07-29 - 2026-MECH-0002606

01:00 PM - 03:00 PM: 903 - Rough

2026-07-20 - 2026-BOILERAC-0000330

11:00 AM - 01:00 PM: 701 - Pressure Test

TBD: 704 - Final - Boiler AC

2026-07-16 - 2026-FIRE-0002899

12:00 PM - 02:00 PM: 303 - Full Rough

2026-07-16 - 2026-ELEC-0002861

12:00 PM - 02:00 PM: 308 - Ceiling

2026-07-15 - 2026-MECH-0002606

01:00 PM - 03:00 PM: 902 - Partial Rough

2026-07-14 - 2026-FIRE-0002899

01:00 PM - 03:00 PM: 303 - Full Rough

2026-07-14 - 2026-COMMCON-0000492

11:00 AM - 01:00 PM: 109 - Other

2026-07-07 - 2026-FIRE-0001583

08:00 AM - 10:00 AM: 411 - Rough

2026-07-06 - 2026-COMMCON-0000492

12:00 PM - 02:00 PM: 107 - Drywall

2026-06-30 - 2026-ELEC-0002861

01:00 PM - 03:00 PM: 308 - Ceiling

2026-06-30 - 2026-FIRE-0001583

08:30 AM - 11:30 AM: 411 - Rough

2026-06-23 - 2026-COMMCON-0000492

11:00 AM - 01:00 PM: 109 - Other

363 N Fairfax St

Directions

Recent Inspections

2026-10-27 - 2025-RESCON-0000440

01:00 PM - 03:00 PM: 109 - Other

2026-10-22 - 2025-RESCON-0000440

11:00 AM - 01:00 PM: Document Review

11:00 AM - 01:00 PM: 109 - Other

11:00 AM - 01:00 PM: 200 - Blown Insulation

2026-10-21 - 2025-RESCON-0000440

09:00 AM - 11:00 AM: 113 - Pre Construction Meeting

2026-10-14 - 2026-ELEC-0002271

08:00 AM - 10:00 AM: 305 - Final - Electrical

2026-10-13 - 2026-ELEC-0002271

08:00 AM - 10:00 AM: 305 - Final - Electrical

08:00 AM - 10:00 AM: 307 - Service Equipment

08:30 AM - 09:30 AM: 313 - Meter Release

2026-10-10 - 2026-ELEC-0001369

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-09 - 2026-ELEC-0001369

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-10-07 - 2025-MECH-0008296

12:00 PM - 02:00 PM: Document Review

2026-10-06 - 2025-MECH-0008296

12:00 PM - 02:00 PM: 904 - Final - Mechanical

2026-10-06 - 2025-PLUMB-0008703

01:00 PM - 03:00 PM: 402 - Final - Plumbing

2026-10-06 - 2026-MECH-0000152

12:00 PM - 02:00 PM: 904 - Final - Mechanical

2026-08-31 - 2026-MECH-0004394

11:00 AM - 01:00 PM: 904 - Final - Mechanical

2026-07-20 - 2026-MECH-0004394

12:00 PM - 02:00 PM: 901 - Pressure Test

2026-07-14 - 2025-ROOFSIDE-0010367

09:00 AM - 11:00 PM: 201 - Final - Roof

2026-07-14 - 2025-ROOFSIDE-0010368

09:00 AM - 11:00 PM: 201 - Final - Roof

2500 E 2nd AVE

Directions

Recent Inspections

2026-10-27 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 107 - Drywall

2026-10-27 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-10-26 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-10-22 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

01:00 PM - 03:00 PM: 112 - Frame

2026-10-22 - 2025-MECH-0007452

08:00 AM - 11:00 AM: 902 - Partial Rough

2026-10-21 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 105 - Exterior Sheathing

11:00 AM - 01:00 PM: 107 - Drywall

2026-10-20 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 107 - Drywall

2026-10-20 - 2025-PLUMB-0010022

12:00 PM - 03:00 PM: 401 - Rough

2026-10-19 - 2025-MECH-0007452

12:00 PM - 02:00 PM: 902 - Partial Rough

2026-10-16 - 2025-BOILERAC-0000874

01:00 PM - 03:00 PM: 703 - Rough

2026-10-15 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-10-14 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-10-14 - 2025-MECH-0007452

12:00 PM - 02:00 PM: 902 - Partial Rough

2026-10-13 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-10-13 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-10-09 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-10-08 - 2025-ELEC-0012459

09:00 AM - 11:00 AM: 300 - Slab

2026-10-07 - 2025-COMMCON-0001894

08:30 AM - 09:30 AM: 107 - Drywall

2026-10-07 - 2025-ELEC-0012459

09:00 AM - 11:00 AM: 300 - Slab

2026-10-06 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 106 - Batt Insulation

11:00 AM - 01:00 PM: 112 - Frame

2026-10-05 - 2025-COMMCON-0001894

09:00 AM - 11:00 AM: 107 - Drywall

TBD: 112 - Frame

2026-10-02 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-10-02 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-10-01 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-10-01 - 2025-ELEC-0012459

08:30 AM - 09:30 AM: 300 - Slab

2026-09-30 - 2026-FIRE-0002246

09:00 AM - 11:00 AM: 411 - Rough

2026-09-30 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-09-29 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-09-26 - 2025-ELEC-0012459

07:00 AM - 01:00 PM: 300 - Slab

2026-09-25 - 2026-FIRE-0002246

08:00 AM - 10:00 AM: 411 - Rough

2026-09-25 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-09-25 - 2025-ELEC-0012459

07:00 AM - 01:00 PM: 300 - Slab

2026-09-25 - 2025-PLUMB-0010022

08:00 AM - 10:00 AM: 401 - Rough

2026-09-24 - 2026-FIRE-0002246

09:00 AM - 11:00 AM: 411 - Rough

2026-09-24 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-09-23 - 2025-MECH-0007452

08:00 AM - 11:00 AM: 903 - Rough

2026-09-22 - 2026-FIRE-0002246

09:00 AM - 11:00 AM: 411 - Rough

2026-09-22 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-09-18 - 2025-COMMCON-0001894

12:00 PM - 02:00 PM: 107 - Drywall

2026-09-18 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-09-16 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-09-14 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-09-10 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 107 - Drywall

11:00 AM - 01:00 PM: 112 - Frame

2026-09-10 - 2025-PLUMB-0010022

08:00 AM - 10:00 AM: 113 - Pre Construction Meeting

2026-09-09 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

01:00 PM - 03:00 PM: 109 - Other

2026-09-08 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 107 - Drywall

2026-09-05 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 112 - Frame

2026-09-04 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 112 - Frame

2026-09-03 - 2025-MECH-0007452

08:00 AM - 11:00 AM: 902 - Partial Rough

2026-09-02 - 2025-COMMCON-0001894

08:30 AM - 09:30 AM: 107 - Drywall

2026-08-28 - 2025-ELEC-0012459

08:30 AM - 09:30 AM: 113 - Pre Construction Meeting

2026-08-26 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-08-20 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-18 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 112 - Frame

2026-08-17 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-12 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-08-10 - 2025-COMMCON-0001894

01:00 PM - 03:00 PM: 112 - Frame

2026-08-04 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-07-14 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-07-14 - 2025-ELEC-0012459

09:00 AM - 11:00 AM: 300 - Slab

2026-07-10 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 112 - Frame

2026-07-09 - 2025-COMMCON-0001894

11:00 AM - 01:00 PM: 113 - Pre Construction Meeting

2026-07-07 - 2025-PLUMB-0010022

09:00 AM - 11:00 AM: 401 - Rough

2026-07-06 - 2025-PLUMB-0010022

08:30 AM - 09:30 AM: 401 - Rough

2026-07-01 - 2026-FIRE-0002311

09:00 AM - 11:00 AM: 412 - Final - Fire Suppression

2026-06-23 - 2025-ELEC-0012459

09:00 AM - 11:00 AM: 300 - Slab

20398 Green Valley Ranch Blvd

Directions

Recent Inspections

2026-10-27 - 2024-COMMCON-0000117

01:00 AM - 03:00 PM: 109 - Other

2026-10-26 - 2026-FIRE-0000895

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-10-26 - 2026-FIRE-0001558

08:00 AM - 10:30 AM: 410 - Underground

2026-10-26 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 308 - Ceiling

2026-10-22 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 109 - Other

2026-10-16 - 2024-BOILERAC-0000054

09:00 AM - 11:00 AM: 704 - Final - Boiler AC

2026-10-16 - 2024-COMMCON-0000117

08:00 AM - 10:00 AM: 109 - Other

2026-10-16 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-10-14 - 2026-FIRE-0000895

01:00 PM - 03:00 PM: 302 - Partial Rough

2026-10-14 - 2026-ELEC-0000357

01:00 PM - 03:00 PM: 305 - Final - Electrical

2026-10-14 - 2026-ELEC-0001095

01:00 PM - 03:00 PM: 308 - Ceiling

2026-10-09 - 2024-COMMCON-0000117

11:45 AM - 12:30 PM: 107 - Drywall

2026-10-01 - 2024-COMMCON-0000117

09:30 AM - 10:30 AM: 107 - Drywall

2026-09-30 - 2024-PLUMB-0000519

12:15 PM - 03:00 PM: 403 - Pressure Test

12:15 PM - 03:00 PM: 405 - Meter Release

2026-09-23 - 2024-MECH-0000458

11:00 AM - 01:00 PM: 903 - Rough

2026-09-23 - 2026-ELEC-0001095

01:00 PM - 03:00 PM: 302 - Partial Rough

01:00 PM - 03:00 PM: 304 - Partial Final

2026-09-22 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-09-14 - 2026-ELEC-0001095

12:00 PM - 02:30 PM: 307 - Service Equipment

2026-09-09 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-09-04 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-09-02 - 2024-COMMCON-0000117

01:00 AM - 03:00 PM: 107 - Drywall

2026-08-21 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 109 - Other

2026-08-21 - 2026-PLUMB-0006818

12:30 PM - 03:00 PM: 404 - Water Service

2026-08-20 - 2026-ROOFSIDE-0001312

09:30 AM - 11:30 AM: 206 - Other

2026-08-20 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 107 - Drywall

2026-08-19 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-17 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 107 - Drywall

01:00 PM - 03:00 PM: 109 - Other

01:00 PM - 03:00 PM: 112 - Frame

2026-08-14 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 303 - Full Rough

2026-08-13 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 107 - Drywall

2026-08-11 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-08-10 - 2024-COMMCON-0000117

10:00 AM - 12:00 PM: 112 - Frame

2026-08-07 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-07 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 313 - Meter Release

12:30 PM - 02:30 PM: 307 - Service Equipment

2026-08-06 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 107 - Drywall

2026-08-04 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-31 - 2024-COMMCON-0000117

11:30 AM - 12:30 PM: 106 - Batt Insulation

2026-07-30 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 106 - Batt Insulation

2026-07-27 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-24 - 2024-COMMCON-0000117

08:00 AM - 10:00 AM: 112 - Frame

2026-07-24 - 2024-MECH-0000458

11:00 AM - 01:00 PM: 903 - Rough

2026-07-21 - 2026-ELEC-0001095

12:30 PM - 02:30 PM: 302 - Partial Rough

2026-07-13 - 2024-MECH-0000458

09:00 AM - 11:00 AM: 903 - Rough

2026-07-10 - 2024-COMMCON-0000117

01:00 PM - 03:00 PM: 106 - Batt Insulation

01:00 PM - 03:00 PM: 112 - Frame

2026-07-07 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 106 - Batt Insulation

2026-07-01 - 2024-PLUMB-0000519

08:30 AM - 10:30 AM: 404 - Water Service

2026-06-22 - 2026-ROOFSIDE-0001312

02:00 PM - 03:00 PM: 205 - Pre Inspection Commercial Flat Roof

2026-06-19 - 2024-COMMCON-0000117

08:30 AM - 09:30 AM: 112 - Frame

1500 N Grant ST

Directions

Recent Inspections

2026-10-27 - 2026-COMMCON-0000699

08:29 AM - 10:30 AM: 108 - Final - Commercial

2026-10-21 - 2026-COMMCON-0000699

08:29 AM - 10:30 AM: 108 - Final - Commercial

2026-10-09 - 2026-ELEC-0003296

08:30 AM - 10:30 AM: 305 - Final - Electrical

2026-10-01 - 2026-ELEC-0003296

10:00 AM - 12:00 PM: 305 - Final - Electrical

2026-09-24 - 2026-ELEC-0003296

08:00 AM - 10:30 AM: 305 - Final - Electrical

2026-08-13 - 2026-ELEC-0003296

08:30 AM - 09:30 AM: 301 - Underground